Fujitsu RX330 manual Installing/removing the server in/from the rack, Rack requirements

Page 35

Hardware installation Installing/removing the server in/from the rack

4.2Installing/removing the server in/from the rack

VCAUTION!

Follow the safety instructions in chapter “Important infor- mation” on page 21 and section “Notes on installing in the rack” on page 30.

At least two people are needed to position the server into/out of the rack.

The rack can tip over when more than one unit is removed.

The server may not occupy the top height unit of the rack (38 HU/42 HU PRIMECENTER Rack and/or DataCenter Rack), as otherwise boards or fans cannot be replaced even with the plug-in module fully extended.

Rack requirements

The rack systems from Fujitsu Siemens Computers (PRIMECENTER Rack and DataCenter Rack) support installation of PRIMERGY servers. Installation in most current rack systems from other manufacturers (3rd party racks) is also supported.

To accommodate the ventilation concept and ensure proper ventilation, any unused areas in the rack must be sealed using dummy covers.

The power is supplied via the multiple socket outlets fitted in the rack.

RX330 S1

Operating manual

35

Image 35
Contents Primergy RX330 S1 Server Certified documentation according to DIN EN ISO Comments… Suggestions… Corrections…Copyright and Trademarks Contents Contents Abbreviations Literature Index Page Concept and target groups for this manual IntroductionDocumentation overview Additional server documentation Documentation overviewSystem board FeaturesIntroduction Further sources of informationUSB port FeaturesAccessible drives Power supplyIRMC with integrated service LAN port Features Server management ServerStart Service and supportRemoteView Notational conventions Notational conventionsCompliance with regulations and standards Technical dataElectrical data hot-plug power supply unit Ventilation clearance Technical dataWeight Mechanical valuesInstallation steps, overview Installation steps, overview Important information SafetyBefore starting up SafetyInstallation and operation Important information Safety Never remove parts of the CD/DVD drive casing Working with CDs/DVDs and CD/DVD drivesLaser information Batteries ESD label Modules with Electrostatic-Sensitive DevicesOther important information CE conformityFCC Class a Compliance Statement CE conformityTransporting the server Important information Packaging information Environmental protectionEnvironmentally-friendly product design and development Energy-saving informationReturns, recycling and disposal Environmental protectionLabels on plastic casing parts Hours Hardware installationMinimum acclimatization time Unpacking the server Unpacking the serverRack requirements Installing/removing the server in/from the rackDataCenter Rack Installing/removing the server in/from the rackPrimecenter Rack Operating manual Mechanical requirements Fitting the support bracket Installation in PRIMECENTER/DataCenter RackRemove the outer telescopic rail Operating manual Racks with installation depth of 735 mm Installation in 3rd party racksPreparing the server Inserting the serverInserting the server Hardware installation Connecting devices to the serverConnecting the keyboard, mouse and monitor Connecting devices to the serverConnecting the server to the mains Connecting the server to the mainsDisconnecting cables Connecting cablesFront of server Starting up and operationControls and displays Controls Indicators on the control panelControls and displays Starting up and operation Indicators on the drives CD/DVD indicatorLED Indicators on the HDD moduleRear of server Global error indicator and ID indicatorLAN indicators Indicators on the connection panel LAN indicatorsStatus Meaning Hot-plug PSU indicatorsSystem already installed Switching the server on and offSwitching the server on and off Switching the server onAfter power failure Switching the server OFFSpecified switch on time / switch off time Ring indicatorConfiguring the server Configuring the serverConfiguring onboard SAS controller ServerStart advantages Configuration with ServerStartConfiguring onboard SAS controller Cleaning the serverConfiguration without ServerStart Cleaning the serverProperty and data protection Bios Setup security functionsPreventing unauthorized Bios Setup calls Preventing unauthorized system accessProtecting the server from being switched off by a program Protecting Bios from being overwrittenPower supply overloaded Troubleshooting and tipsPower-on indicator remains unlit Power cable incorrectly connectedScreen remains blank Server switches itself offNo mouse pointer displayed on screen Flickering stripes on monitor screenNo screen display or display drifts Incorrect date and time System will not bootMouse controller disabled SAS configuration incorrectRAID controller is not configured for this drive Drives reported as dead when starting systemError message on screen RAID controller configuration incorrectPage Hot-plug components Hot-plug power supply unitsRemove the dummy module Hot-plug power supply unitsHot-plug components Installing/removing the hot-plug power supply unitReplacing the hot-plug power supply unit Hot plug hard disk drives HDD module and dummy module Hot plug hard disk drivesHandling hard disk drives and HDD modules Removing the dummy module Removing/Installing the dummy moduleUnlocking the HDD module Installing/removing the HDD moduleInstalling the HDD module Installing the HDD moduleRemoving the HDD module Vcaution Abbreviations Abbreviations IRMC LBA RAM SEL Literature Primergy ServerView Suite Literature Primergy ServerView Suite ServerView S2Primergy ServerView Suite ServerView CD-RW DVD-RW IndexDVD IndexUSB Dimensions Electrical data Index