Fujitsu RX330 Operating manual

Page 41

Hardware installation Installing/removing the server in/from the rack

Installing the telescopic rail with variable support

4

1

a

2

3

Figure 5: Fit the left telescopic rail in the PRIMECENTER/DataCenter Rack

ÊPosition the left-hand rail (1) in the support bracket with the vertical lug (a) in the middle square catch.

ÊPress the left rail together until its front end passes behind the front left support upright (2), then release.

ÊSecure the rail on the front left support upright (3) and the support bracket in the rack (4) with two (M5) screws each.

ÊRepeat the steps with the right telescopic rail (to be secured to the right support uprights).

ÊFit the PRIMECENTER/DataCenter Rack cable management as described in the technical manual for the rack.

ÊInsert the server (see the “Inserting the server” on page 43 section).

ÊRoute the cables once the server has been inserted, as described in the Technical Manual for the rack in question.

RX330 S1

Operating manual

41

Image 41
Contents Primergy RX330 S1 Server Certified documentation according to DIN EN ISO Comments… Suggestions… Corrections…Copyright and Trademarks Contents Contents Abbreviations Literature Index Page Concept and target groups for this manual IntroductionDocumentation overview Additional server documentation Documentation overviewIntroduction FeaturesFurther sources of information System boardAccessible drives FeaturesPower supply USB portIRMC with integrated service LAN port Features Server management ServerStart Service and supportRemoteView Notational conventions Notational conventionsCompliance with regulations and standards Technical dataElectrical data hot-plug power supply unit Weight Technical dataMechanical values Ventilation clearanceInstallation steps, overview Installation steps, overview Important information SafetyBefore starting up SafetyInstallation and operation Important information Safety Never remove parts of the CD/DVD drive casing Working with CDs/DVDs and CD/DVD drivesLaser information Batteries ESD label Modules with Electrostatic-Sensitive DevicesFCC Class a Compliance Statement CE conformityCE conformity Other important informationTransporting the server Important information Environmentally-friendly product design and development Environmental protectionEnergy-saving information Packaging informationReturns, recycling and disposal Environmental protectionLabels on plastic casing parts Hours Hardware installationMinimum acclimatization time Unpacking the server Unpacking the serverRack requirements Installing/removing the server in/from the rackDataCenter Rack Installing/removing the server in/from the rackPrimecenter Rack Operating manual Mechanical requirements Fitting the support bracket Installation in PRIMECENTER/DataCenter RackRemove the outer telescopic rail Operating manual Racks with installation depth of 735 mm Installation in 3rd party racksPreparing the server Inserting the serverInserting the server Hardware installation Connecting devices to the serverConnecting the keyboard, mouse and monitor Connecting devices to the serverConnecting the server to the mains Connecting the server to the mainsDisconnecting cables Connecting cablesFront of server Starting up and operationControls and displays Controls Indicators on the control panelControls and displays Starting up and operation Indicators on the drives CD/DVD indicatorLED Indicators on the HDD moduleRear of server Global error indicator and ID indicatorLAN indicators Indicators on the connection panel LAN indicatorsStatus Meaning Hot-plug PSU indicatorsSwitching the server on and off Switching the server on and offSwitching the server on System already installedSpecified switch on time / switch off time Switching the server OFFRing indicator After power failureConfiguring the server Configuring the serverConfiguring onboard SAS controller ServerStart advantages Configuration with ServerStartConfiguration without ServerStart Cleaning the serverCleaning the server Configuring onboard SAS controllerPreventing unauthorized Bios Setup calls Bios Setup security functionsPreventing unauthorized system access Property and data protectionProtecting the server from being switched off by a program Protecting Bios from being overwrittenPower-on indicator remains unlit Troubleshooting and tipsPower cable incorrectly connected Power supply overloadedScreen remains blank Server switches itself offNo mouse pointer displayed on screen Flickering stripes on monitor screenNo screen display or display drifts Mouse controller disabled System will not bootSAS configuration incorrect Incorrect date and timeError message on screen Drives reported as dead when starting systemRAID controller configuration incorrect RAID controller is not configured for this drivePage Hot-plug components Hot-plug power supply unitsRemove the dummy module Hot-plug power supply unitsHot-plug components Installing/removing the hot-plug power supply unitReplacing the hot-plug power supply unit Hot plug hard disk drives HDD module and dummy module Hot plug hard disk drivesHandling hard disk drives and HDD modules Removing the dummy module Removing/Installing the dummy moduleUnlocking the HDD module Installing/removing the HDD moduleInstalling the HDD module Installing the HDD moduleRemoving the HDD module Vcaution Abbreviations Abbreviations IRMC LBA RAM SEL Literature Primergy ServerView Suite Literature Primergy ServerView Suite ServerView S2Primergy ServerView Suite ServerView CD-RW DVD-RW IndexDVD IndexUSB Dimensions Electrical data Index