Cisco Systems 100/200/300/400 Verifying Contents, Inspecting for Damage, Installing the CDEs

Page 43

Chapter 3 Installing the Content Delivery Engines

Verifying Contents

Verifying Contents

To verify that your shipment is complete, make sure that you received everything on your packing list, and then compare your packing list to your order.

If any items are missing or if you need additional information, contact Cisco Technical Support at the following URL:

www.cisco.com/techsupport

Inspecting for Damage

After you verify that all of the equipment is included, carefully examine the CDEs, cards, power supplies, and cables for any damage resulting from shipping. If you suspect any damage from shipping, contact your local freight carrier for procedures on damage claims.

If you observe any physical defects in the items you ordered, obtain standard warranty service by delivering the defective part, accompanied by a copy of the dated proof-of-purchase, to the Cisco Systems Corporate Service Center or an authorized Cisco Systems service center during the applicable warranty period. Contact Cisco Technical Support for the location of your nearest service center.

Note Before proceeding with the installation, verify that all of the ordered parts are present and in good condition. Keep a record of the parts and serial numbers. If any parts are missing or damaged, contact your sales representative.

Installing the CDEs

Installing the CDS consists of the following tasks:

Reviewing Rack Installation Safety Guidelines, page 3-3

Preparing the CDEs for Rack Installation, page 3-4

Installing CDEs in the Rack, page 3-5

Making Physical Connections, page 3-5

Installing or Removing Disk Drives, page 3-9

Reviewing Rack Installation Safety Guidelines

Before installing your device in a rack, review the following guidelines:

The equipment is to be installed by a trained service person.

The equipment is to be installed in a Restricted Access Location.

Handles on the equipment are provided for positioning purpose only, not for lifting the chassis.

The customer should follow their own company guidelines and governing regulations for handling heavy equipment.

Two or more people are required to install the device in a rack.

Ensure that the room air temperature is below 95°F (35°C).

Cisco Content Delivery Engine 100/200/300/400 Hardware Installation Guide

 

OL-13478-03

3-3

 

 

 

Image 43
Contents Americas Headquarters MarchCisco Systems, Inc. All rights reserved N T E N T S Connecting Network Cables Ethernet Connector Pin Assignments B-2 OL-13478-03 Document Organization Document Revision HistoryDate Change Summary Chapter Description ObjectivesAudience Related DocumentationCisco Internet Streamer CDS 2.x Product Documentation Conventions Safety Information Referral WarningAvvertenza Importanti Istruzioni Sulla Sicurezza Warnung Wichtige SicherheitshinweiseAviso Instruções Importantes DE Segurança TA Vare PÅ Disse InstruksjoneneXii GEM Disse Anvisninger Xiv Obtaining Documentation and Submitting a Service Request Xvi Cisco Internet Streamer CDS Overview Overview of the Content Delivery EnginesOnDemand Application Cisco TV CDS OverviewVideo Accelerator Software CDE200 Front View Hardware FeaturesEth5 eth3 Processor Memory Drives Rack Unit EthernetInterface Processor Memory Drives GE Ports Interface Control Buttons10 CDE200 Front Panel Control Buttons 12 CDE400 Back Panel Control Buttons LED IndicatorsColor State Description LED15 CDE300 Front Panel LEDs 17 CDE100 Connector Locations Input/Output Ports and ConnectorsCDE200 Connector Locations CDE400 Connector Locations OL-13478-03 Preventing Electrostatic Discharge Damage Site RequirementsEnvironmental, Physical, and Power Specifications Safety Warnings OL-13478-03 Page General Precautions Safety GuidelinesAC Power Option Warnings DC Power Option WarningsProtecting Against Electrostatic Discharge Intended Uses Safety InformationIf AC Power Supplies Are Installed Emissions DisclaimerAmps Statement If DC Power Supplies Are InstalledTemperature and Ventilation Server Types Installing the Content Delivery EnginesUnpacking the Box Tools and Parts RequiredInstalling the CDEs Verifying ContentsInspecting for Damage Preparing the CDEs for Rack Installation Making Physical Connections Installing CDEs in the RackConnecting Power Cords CDE300 SX Version Connector Locations Connecting Network Cables Interface Switch Port Mbps Installing or Removing Disk DrivesCDE400 Disk Drive Locations Statement 11 Disk Drive Tray Installation and Removal Before You Begin Ethernet Stream Running the Bios Setup UtilityInstallation and Configuration Order Ethernet Management Gigabit Ethernet Ports Management PortsRunning the Bios Setup Utility for the CDE100 Boot Settings Menu Boot Device Priority Screen Advanced Settings Menu Set the Serial Port2 Address option to Disabled 10 Exit Options Screen Running the Bios Setup Utility for the CDE200 Set the QuickBoot Mode option to Enabled 14 Hard Disk Drives Screen Set the Com Port Address option to On-board COM a Model CDE200 Installing the SoftwareAssigning the Primary Interface Initially Configuring a CDEVerifying the Cdsm Running the Setup Utility18 Cdsm Login Documentation section on OL-13478-03 Troubleshooting Ethernet Adapters Hardware TroubleshootingTroubleshooting Sata Drives Specifications Technical SpecificationsCDE200 CDE100CDE400 CDE300Data Rate ManagementInput Cables Description Pin Serial Console Interface Connector Pin AssignmentsSerial Port Connector Ethernet Connector Pin AssignmentsPin T568B 100BASE-T Signal Ethernet Port ConnectorRJ-45 Pin End Wire Color Diagram End Computer Cable Pin AssignmentsWhite/Orange White/Green Blue White/Blue White/Brown OL-13478-03 Processor WeightFan Assembly Management InterfaceTransport Content Storage CapacityIngest Interface Stream InterfacesCDE200 IBM Cached Content CapacityEthernet Interfaces Scsi Controllers Figure C-1shows the location of all connectors for a CDE100 Connector Pin AssignmentsFigure C-3 CDE200 IBM Connector Locations Eth1 Eth0 Eth3 eth5 Eth6 Eth5 Eth8 Eth2 Eth4 Eth7 Eth1 Eth3 DC Power Overview Connecting DC PowerFigure D-2 CDE200 Rear Panel Connecting DC Power to a CDE200Star washer PM ground ring lug Nut Connecting DC Power to a CDE200 section on page D-2 Disconnecting Power and Replacing a PM on a CDE200Figure D-5 CDE300 Rear Panel Connecting DC Power to a CDE300Figure D-6 CDE300 Building/PM Ground Stud Order Disconnecting Power and Replacing a PM on a CDE300 Connecting DC Power to a CDE40048 VDC Figure D-8 CDE400 PM Ground Stud Order Disconnecting Power and Replacing a PM on a CDE400 DC Power Cable Connector and Pinouts OL-13478-03 Numerics IN-2 IN-3 IN-4 IN-5 IN-6