Chapter 3 Installing the Content Delivery Engines
Installing the CDEs
•Do not block any air vents; usually 6 inches (15 cm) of space provides proper airflow.
•Plan the device installation starting from the bottom of the rack.
•Install the heaviest device in the bottom of the rack.
•Do not extend more than one device out of the rack at the same time.
•Remove the rack doors and side panels to provide easier access during installation.
•Connect the device to a properly grounded outlet.
•Do not overload the power outlet when installing multiple devices in the rack.
•Do not place any object weighing more than 110 lb (50 kg) on top of
Preparing the CDEs for Rack Installation
Verify correct hardware configuration by performing the following steps:
Step 1 Remove the top cover on the chassis by removing the screws and lifting the cover from the chassis. Step 2 Configure the applicable chassis as follows:
CDE100
a.Set all dip switches at the back of the disk array case to the OFF (down) position.
b.Make sure the
CDE200
a.Make sure the
b.Disable the onboard SCSI controller by connect pins 2 and 3 (instead of 1 and 2) for the jumper labeled
CDE300
a.Make sure the
b.Disable the onboard SCSI controller by connect pins 2 and 3 (instead of 1 and 2) for the jumper labeled
CDE400
a.Make sure the
Step 3 Replace the top cover on the chassis.
Cisco Content Delivery Engine 100/200/300/400 Hardware Installation Guide
|
| |
|