Allied Telesis AT-PWR06, AT-DC2552XS, AT-FAN06 manual QSFP+ LEDs QSFP+ LED is described in Table

Page 24

Chapter 1: Overview

QSFP+ Slot LEDs Each QSFP+ port has one link/activity LED labeled LINK/ACT. These LEDs are shown in Figure 4.

QSFP+ LEDs

Figure 4. QSFP+ LEDs

The QSFP+ LED is described in Table 3.

Table 3. QSFP+ LED

LED

State

Description

 

 

 

 

 

 

 

Solid green

The QSFP+ transceiver has established a

 

 

link to a network device.

 

 

 

Link/Activity

Flashing

The QSFP+ transceiver is receiving or

 

green

transmitting packets to a network device.

 

 

 

 

 

The QSFP+ slot is empty or the QSFP+

 

Off

transceiver has not established a link to a

 

 

network device.

 

 

 

24

Image 24
Contents Installation Guide Page Electrical Safety and Emissions Standards TickTranslated Safety Statements Contents Page Figures Figures Tables Tables Preface Document Conventions Contacting Allied Telesis Preface Overview ChapterAT-DC2552XS Features FunctionsInstallation Options Optional QSFP+ Transceivers  AT-QSFPSR 40GBASE-SR4 MPOLED LED FANAT-DC2552XS Rear Panel Stack Installation Guide for AT-2552XS L2 Data Center Switch Cable Type 10Mbps 100Mbps 1000Mbps LEDs LEDQSFP+ LEDs QSFP+ LED is described in Table Power FaultLink ACT LED LinkFAN1 FAN2AC OK Console Port AT-PWR06 Power Supply Module Stack Installation Guide for AT-2552XS L2 Data Center Switch AT-FAN06 Fan Module Beginning the Installation Installation Overview Step ProcedureReviewing Safety Precautions Beginning the Installation Stack Installation Guide for AT-2552XS L2 Data Center Switch Beginning the Installation Planning the Installation Unpacking the Switch AT-DC2552XS SwitchAT-PWR06 Power Supply AT-FAN06 Fan Module Installing the Switch and Modules Installing the Switch on a Desktop Installing the Switch in an Equipment Rack Possible Bracket LocationsInstalling the Switch and Modules Mounting the Switch in an Equipment Rack Installing and Replacing AT-PWR06 Power Supply Module Installing Power Supply ModuleInsert AT-PWR06 Module Into Chassis Replacing Power Supply Module Tighten AT-PWR06 Captive ScrewsInstalling Power Supply Blank Cover Installing and Replacing AT-FAN06 Fan Module Installing Fan ModuleStack Installation Guide for AT-2552XS L2 Data Center Switch Replacing Fan Module Installing the SFP+ and QSFP+ Transceivers and Cables Installing SFP+ Transceivers and Cables 10GBASE-SRAT-SP10SR 10GBASE-LRInstalling SFP+ Transceiver Removing SFP+ Dust Cover Installing a SFP+ Direct Attach Cables Installing the SFP+ and QSFP+ Transceivers and Cables Installing QSFP+ Transceivers and Cables 40GBASE-SR4AT-QSFPSR Installing the SFP+ and QSFP+ Transceivers and Cables QSFP+ Mthtp Installing the SFP+ and QSFP+ Transceivers and Cables Powering the Switch Powering On the Switch Stack Installation Guide for AT-2552XS L2 Data Center Switch Turn Off the switch Managing the Switch Connecting the Console Port Local ManagementStack Installation Guide for AT-2552XS L2 Data Center Switch NET Mgmt Cable Installation Remote Network ManagementStack Installation Guide for AT-2552XS L2 Data Center Switch Managing the Switch Troubleshooting Troubleshooting Stack Installation Guide for AT-2552XS L2 Data Center Switch Troubleshooting Technical Specifications Physical SpecificationsEnvironmental Specifications Appendix aPower Specifications CertificationsQuality and Reliability MtbfRJ-45 Twisted Pair Port Pinouts TX+ RX+Pinout Pair Stack Installation Guide for AT-2552XS L2 Data Center Switch Appendix a Technical Specifications