Allied Telesis AT-PWR06, AT-DC2552XS, AT-FAN06 manual Installing Power Supply Blank Cover

Page 51

Installing Power

Supply Blank

Cover

Stack Installation Guide for AT-2552XS L2 Data Center Switch

Note

If a new AT-PWR06 power supply module is not available to replace the module you are removing, perform the procedure outlined in “Installing Power Supply Blank Cover” on page 51.

4.Slowly insert the new AT-PWR06 power supply module into the PSU slot until it is flush with the front of the chassis.

5.Tighten the captive screws to fasten of the power supply module to the chassis.

6.Turn the power on to the newly installed AT-PWR06 power supply module by connecting the AC power cord.

If you have removed an AT-PWR06 power supply module from the chassis and a replacement power supply module is not available, the blank power supply cover should be installed to insure proper airflow in the chassis.

Caution

The PSU blank cover should be installed if an AT-PWR06 power supply module is not installed in the power supply slot. This blank cover assures that the correct airflow across the components within the chassis when a power supply module is not installed.

Perform the following procedure to install the blank power supply cover:

1.Locate the blank power supply cover that was originally shipped with the chassis.

2.Remove the AT-PWR06 power supply module by following steps 1 - 3 in “Replacing Power Supply Module” on page 50.

3.Once the AT-PWR06 power supply module has been removed, place the blank power supply cover over the vacant power supply slot.

4.Tighten the captive screws on the power supply blank cover.

51

Image 51
Contents Installation Guide Page Tick Electrical Safety and Emissions StandardsTranslated Safety Statements Contents Page Figures Figures Tables Tables Preface Document Conventions Contacting Allied Telesis Preface Chapter OverviewFunctions AT-DC2552XS FeaturesInstallation Options  AT-QSFPSR 40GBASE-SR4 MPO Optional QSFP+ TransceiversLED FAN LEDAT-DC2552XS Rear Panel Stack Installation Guide for AT-2552XS L2 Data Center Switch Cable Type 10Mbps 100Mbps 1000Mbps LED LEDsQSFP+ LEDs QSFP+ LED is described in Table Fault PowerLink Link ACT LEDFAN2 FAN1AC OK Console Port AT-PWR06 Power Supply Module Stack Installation Guide for AT-2552XS L2 Data Center Switch AT-FAN06 Fan Module Beginning the Installation Step Procedure Installation OverviewReviewing Safety Precautions Beginning the Installation Stack Installation Guide for AT-2552XS L2 Data Center Switch Beginning the Installation Planning the Installation AT-DC2552XS Switch Unpacking the SwitchAT-PWR06 Power Supply AT-FAN06 Fan Module Installing the Switch and Modules Installing the Switch on a Desktop Possible Bracket Locations Installing the Switch in an Equipment RackInstalling the Switch and Modules Mounting the Switch in an Equipment Rack Installing Power Supply Module Installing and Replacing AT-PWR06 Power Supply ModuleInsert AT-PWR06 Module Into Chassis Tighten AT-PWR06 Captive Screws Replacing Power Supply ModuleInstalling Power Supply Blank Cover Installing Fan Module Installing and Replacing AT-FAN06 Fan ModuleStack Installation Guide for AT-2552XS L2 Data Center Switch Replacing Fan Module Installing the SFP+ and QSFP+ Transceivers and Cables 10GBASE-LR Installing SFP+ Transceivers and Cables10GBASE-SR AT-SP10SRInstalling SFP+ Transceiver Removing SFP+ Dust Cover Installing a SFP+ Direct Attach Cables Installing the SFP+ and QSFP+ Transceivers and Cables Installing QSFP+ Transceivers and Cables 40GBASE-SR4AT-QSFPSR Installing the SFP+ and QSFP+ Transceivers and Cables QSFP+ Mthtp Installing the SFP+ and QSFP+ Transceivers and Cables Powering the Switch Powering On the Switch Stack Installation Guide for AT-2552XS L2 Data Center Switch Turn Off the switch Managing the Switch Local Management Connecting the Console PortStack Installation Guide for AT-2552XS L2 Data Center Switch Remote Network Management NET Mgmt Cable InstallationStack Installation Guide for AT-2552XS L2 Data Center Switch Managing the Switch Troubleshooting Troubleshooting Stack Installation Guide for AT-2552XS L2 Data Center Switch Troubleshooting Appendix a Technical SpecificationsPhysical Specifications Environmental SpecificationsMtbf Power SpecificationsCertifications Quality and ReliabilityTX+ RX+ RJ-45 Twisted Pair Port PinoutsPinout Pair Stack Installation Guide for AT-2552XS L2 Data Center Switch Appendix a Technical Specifications