Mounting the Liebert XDV

Figure 11 Mounting hole locations—standard mounting method

Rear of

Liebert XDV

Front of

Liebert XDV

Bolt 1/4" - 20 (2 places, typ.)

Fan tray removed to show mounting location(s) of 1/4" - 20 bolts

Figure 12 Mounting hole locations—alternate mounting points

Front of Liebert XDV

13/16"

(21mm)

 

B

 

B

 

A

11"

A

 

 

 

 

 

 

 

(279mm)

1

20-7/8"

(530mm)

 

120-5/8"

(524mm)

AA

7-1/16"

1 (179mm)

Notes

1.These dimensions may be used when attaching Liebert XDV to a non-Liebert cabinet.

2.Drill clearance holes as indicated:

"A" #10-32 screw--0.22" (5mm) diameter

"B" 1/4 - 20 bolt--0.28" (7mm) diameter.

3.Field to supply #10/32 screws, quantity of 4.

Factory to supply 1/4 - 20 bolts, quantity of 20.

Rear of Liebert XDV

BOTTOM VIEW

DPN000770

 

Page 7, Rev. 5

11

Image 17
Contents Liebert XDV Fluorinated Greenhouse Gas Requirements-European Union General Safety GuidelinesTable of Contents Maintenance Installation Checklist and System Fill for StartupSpecifications ElectricalFigures Page Liebert XDV component locations Example XDV10BKInstallation Considerations Pre-Installation ChecksInstallation ReferencesGeneral Product Information Product/System DescriptionChecking and Unpacking Recyclable Packaging Equipment InspectionUnpacking the Unit Domestic Packaging Unit HandlingRemoving export shipping package Export PackagingRemoving Liebert XDV from shipping pallet Removing the Liebert XDV from the PalletMechanical Considerations Determining Placement in the Conditioned SpaceDimensional data Changing the Liebert XDV’s air intake location Changing the Air Intake LocationBolting Liebert XDV to Top of Cabinet Mounting the Liebert XDV on Top of the CabinetMounting the Liebert XDV Bottom View Mounting clip placement Using Supplied Clips for MountingSuspended Mounting Method Suspension hardware and bracket dimensional data11mm 22mm Top View 2 64mm 76mm 102mm DPN000770 Pg , RevSuspending the Liebert XDV from Overhead Structures Suspending the Liebert XDV from UnistrutsSuspending Liebert XDV from the overhead structure Stacking configuration offset Mounting Liebert XDVs in Stacked SetupStacked Liebert XDVs suspended from Unistruts Hanging Stacked Liebert XDVs from UnistrutsHanging Stacked Liebert XDVs from the Overhead Structure Piping System Connection ConfigurationEuropean Union Fluorinated Greenhouse Gas Requirements Piping Connections to Liebert XDP or Liebert XDC Connection Methods and PointsRight Side Liebert XDV Holding Charge-Hard-Piped Units Hard Piped Connection SizesBrazing Preparations-Hard-Piped Units Recommended Piping SizeBranch piping sizes for refrigerant loop Connection Methods-One-Shot ConnectionsRefrigerant Charge-Pre-Charged Option Field Installation of Liebert Flex Pipe Kit on Liebert XDVConnecting Liebert XD Flex Pipe to Liebert XDV Modules Tools Required Liebert XD prefabricated piping assemblyOvertighten With wrenchReturn Piping mains without Liebert XDV and Liebert Flex Pipe InsulationElectrical Connecting High Voltage Cables for CSA/C-US Certified UnitsRear Liebert XDV Rear of Liebert XDVLiebert XDV electrical connections for CE-approved units Rear View of Liebert Xdvto be N.E.C. Class Connecting Low Voltage Wiring-OptionalCondensate Detection Connections Installation Checklist and System Fill for Startup Checklist for Proper InstallationOperation Start the Liebert XDVFluorinated Greenhouse Gas Requirements Internal AccessMaintenance Accessing internal electrical components Accessing Internal Electrical ComponentsTo remove the fan tray Liebert XDV10 specifications SpecificationsLiebert XDV8 specifications Liebert XD Liebert Flex Pipe assemblies, supply and return Page Iti Ne tTi n That