General product information

Removing the Liebert XDV from the Pallet

1.Unfold the unit bag to expose the Liebert XDV.

2.Verify the nameplate information found on the Liebert XDV against the bill of lading. If the information does not match the product specified, contact your local Liebert sales representative.

3.At least two properly trained personnel may lift the Liebert XDV off the pallet and onto a flat surface.

4.To protect the Liebert XDV’s paint, lay non-abrasive material, longer than the unit, on the flat surface before moving the Liebert XDV.

Figure 7 Removing Liebert XDV from shipping pallet

Removing the Liebert XDV from its shipping pallet requires two people.

7

Image 13
Contents Liebert XDV Fluorinated Greenhouse Gas Requirements-European Union General Safety GuidelinesTable of Contents Maintenance Installation Checklist and System Fill for StartupSpecifications ElectricalFigures Page Liebert XDV component locations Example XDV10BKInstallation Considerations Pre-Installation ChecksInstallation ReferencesChecking and Unpacking Product/System DescriptionGeneral Product Information Recyclable Packaging Equipment InspectionUnpacking the Unit Domestic Packaging Unit HandlingRemoving export shipping package Export PackagingRemoving Liebert XDV from shipping pallet Removing the Liebert XDV from the PalletDimensional data Determining Placement in the Conditioned SpaceMechanical Considerations Changing the Liebert XDV’s air intake location Changing the Air Intake LocationMounting the Liebert XDV Mounting the Liebert XDV on Top of the CabinetBolting Liebert XDV to Top of Cabinet Bottom View Mounting clip placement Using Supplied Clips for MountingSuspended Mounting Method Suspension hardware and bracket dimensional data11mm 22mm Top View 2 64mm 76mm 102mm DPN000770 Pg , RevSuspending the Liebert XDV from Overhead Structures Suspending the Liebert XDV from UnistrutsSuspending Liebert XDV from the overhead structure Stacking configuration offset Mounting Liebert XDVs in Stacked SetupStacked Liebert XDVs suspended from Unistruts Hanging Stacked Liebert XDVs from UnistrutsHanging Stacked Liebert XDVs from the Overhead Structure European Union Fluorinated Greenhouse Gas Requirements System Connection ConfigurationPiping Piping Connections to Liebert XDP or Liebert XDC Connection Methods and PointsRight Side Liebert XDV Holding Charge-Hard-Piped Units Hard Piped Connection SizesBrazing Preparations-Hard-Piped Units Recommended Piping SizeBranch piping sizes for refrigerant loop Connection Methods-One-Shot ConnectionsConnecting Liebert XD Flex Pipe to Liebert XDV Modules Field Installation of Liebert Flex Pipe Kit on Liebert XDVRefrigerant Charge-Pre-Charged Option Tools Required Liebert XD prefabricated piping assemblyOvertighten With wrenchReturn Piping mains without Liebert XDV and Liebert Flex Pipe InsulationElectrical Connecting High Voltage Cables for CSA/C-US Certified UnitsRear Liebert XDV Rear of Liebert XDVLiebert XDV electrical connections for CE-approved units Condensate Detection Connections Connecting Low Voltage Wiring-OptionalRear View of Liebert Xdvto be N.E.C. Class Installation Checklist and System Fill for Startup Checklist for Proper InstallationOperation Start the Liebert XDVMaintenance Internal AccessFluorinated Greenhouse Gas Requirements Accessing internal electrical components Accessing Internal Electrical ComponentsTo remove the fan tray Liebert XDV10 specifications SpecificationsLiebert XDV8 specifications Liebert XD Liebert Flex Pipe assemblies, supply and return Page Iti Ne tTi n That