Piping
6.4Hard Piped Connection Sizes
Supply piping connection is 1/2" OD copper pipe and return piping connection is 5/8" OD copper.
6.4.1Holding Charge—Hard-Piped Units
The Liebert XDV in
To vent the holding charge:
1.Find the Schrader valve that contains the nitrogen holding charge in the Liebert XDV (see Figure 24).
2.Vent the holding charge by depressing the pin in the valve.
3.Replace and secure the cap on the Schrader valve.
Figure 24 Piping location and connection sizes—hard-piped units
| Top View of | |
Supply | Liebert XDV | |
Schrader Valve | ||
Connection | ||
| ||
1/2" | SCHRADER VALVE | |
| ||
| SUPPLY (IN) | |
| RETURN (OUT) | |
Return | ||
Connection | ||
(29mm) | 5/8" | |
| ||
3/4" | Rear of Liebert XDV | |
(19mm) | ||
DPN000770 | ||
(67mm) | Page 4, Rev. 5 |