4Commissioning and Preventive Maintenance

4.1.Pre-Commissioning Inspection

Environment

1.Ensure the DC system environment is suitable for operation.

2.Ensure that there is sufficient clearance around the system for service.

3.Ensure that there is no sign of damage to the DC system.

4.Consult with customer to disable installed customer alarms before servicing the unit. This will allow the unit to be serviced without creating false alarms.

Electrical Installation

1.Ensure that the DC wiring is properly installed, sized, terminated and identified.

2.Ensure that the AC wiring is properly installed, sized, terminated and identified.

3.Ensure that the battery is properly connected to the System.

4.Ensure that the DC output over-current protection devices are adequate for the size of wiring installed.

5.Ensure that the DC Positive is bonded to central office ground (- 48 volt system).

6.Note the resistance of the ground bond.

7.Note any currents flowing in the ground.

8.Record ambient temperature.

9.Verify that the battery polarity is correct.

10.If a battery disconnect device(s) is/are present, note the following for each device:

a.DC Voltage Rating.

b.DC Current Rating

c.Interrupting Current Rating

Battery Visual and Safety Inspection

1.Check the mechanical integrity of the battery framing, racking, or cabinet.

2.Check that the battery framing, racking or cabinet is adequately secured to the floor.

3.Check compliance with seismic zone requirements.

4.Check the general appearance and cleanliness of the battery.

5.Record the manufacturer, model number, and capacity of the battery string(s) on Site Form.

6.Record the batch number, date code, and serial number of each cell or mono-block, and any other pertinent information that is available on the battery cells on the Site Form.

7.Check that the cell or mono-block numbering starts at the positive battery string terminal and is correct.

8.Check that anti-oxidation compound is properly applied.

9.Visually inspect each cell for: a. Cracks.

Image 32
Contents VDC Power Systems Table of Contents Commissioning and Preventive Maintenance APC Worldwide Customer Support Limited Product Warranty Revision History Revision Date DescriptionSafety First General PrecautionsGeneral Information How to Use This ManualIntroduction 1 MX28B-1200 -48 VDC Power Plant Rectifier Bay 2 MX28B Block Diagram Installation Mechanical InstallationUnpacking Equipment Room / LocationPower Bus Connections Mounting2 MX28B-1200-2400 has a maximum Circuit Breaker/LVD Ribbon Cable Connections 5 Circuit Breaker / LVD Expansion BoardVentilation AC Power ConnectionsFuse Alarm Ribbon Cable Connections 1 AC Input Wiring Battery Connections Planning the Battery InstallationConnecting the Battery Cables 1 Battery Cable Connection Locations2 Battery Probe Connection DC System GroundingDC Power Output Over-Current Protection DC Plug-in Circuit BreakersBreaker Part Number Rating 2 Plug-in Circuit Breakers DC Bolt-in Circuit Breakers 4 Bolt-in Circuit BreakersTelecom Fuses 5 Telecom FusesInstallation of Circuit Breakers and Fuses Plug-in Circuit Breaker InstallationBolt-in Circuit Breaker Installation 2 Circuit Breaker Alarm WiringTelecom Fuse Installation GMT Fuse InstallationLoad Connections Cable Size ConsiderationsCircuit Breaker Connections 1 to 50 Amps Circuit Breaker Connections 60-100 AmpsMonitoring and Relay Output Connections GMT Fuse ConnectionsFront Panel DB9 Connection Smart Cable DB9 ConnectionRJ45 Ethernet Connector Relay Output ConnectionsExternal Alarm Input Connections NO-NC-CRectifier Module Installation Commissioning and Preventive Maintenance Electrical InstallationBattery Visual and Safety Inspection Pre-Commissioning InspectionInitial Set-up AC Power UpCommissioning DC Power Up Battery Power UpRectifier Test LVD TestBattery Temperature Compensation Circuit Breaker/ Fuse TestUser Inputs Output RelaysFinal Inspection Rectifier Management OperationTechnical Description System Management System Output CapacitySystem Voltage Control System CurrentBattery Management System Status and Alarm ReportingBattery Charging and Protection DC DistributionFront Panel User Interface Controls and IndicatorsBattery/Load Low Voltage Disconnect Status Alarms System Modules Batt PIN OEM Parameter Locations, Descriptions, and Default ValuesAlarm Item No AlarmsAddress SwitzerBatt HT Alm Batt HT Thr70.0 C Batt HV AlmCir Bkr 1 Alm m+ MajorCir Bkr 72 Almm+ Comp HkneeFuse 1 Alm Fuse 16 AlmHw Batt C Almm+ MinorLVD Reset LVD Option48.00 LVD TripOut-Rly 1 Dly m+ SecOut-Rly 6 Dly m+ Relay MajorDisable Rect 1 DescMRF28H54 Rect 1ofN Almm+Sys HV Alm Sys HV ThrSys LT Alm Sys LT ThrTime 90025SYS MS System Module SET-ALM Setup DA Control Unit Menu StructureV e l C o n d L e v e l I r d L e v e l U r t h L e v e l SYS Sysin Modrec AM Info Modfuse LM Alias Fuse MOD Modlvd Modlvd LM Param Section Alarm Outputs Output RelaysFront Panel LED Indicators External Alarm Inputs Input Relays Command and Monitoring Protocol Remote MonitoringDescription Physical ConnectionsPreventive Maintenance System Visual and Safety InspectionEquipment InspectionRectifier Current Test TestSystem Voltage Test Rectifier Alarm Test System Temperature TestBattery Current Test Rectifier Current Share TestBattery Temperature Test Battery Preventive Maintenance ProcedureFinal Inspection Specifications AC Input1MRF28H54BV Rectifiers 1MRF28H54BV50 RectifiersVDC RectifiersPower Shelf Control Unit Compliance MechanicalEnvironmental APC Worldwide Customer Support US and CanadaToll Free WorldwideLimited Product Warranty