b.Case leaks.
c.Post- seal leaks.
d.Pressure relief valve leaks (VRLA only).
e.Case swelling (VRLA only).
f.Case swelling (VRLA only).
10.Check the torque of all battery inter- cell connector in accordance with the battery manufacturer’s specifications.
4.2. Commissioning
Initial Set-up
1.Remove all rectifiers. Ensure that the float/equalise switch is on float.
2.Disconnect battery by removing a link in each string or opening the battery disconnects.
3.Check that battery voltage does not appear on the system bus.
4.Disconnect all loads.
AC Power Up
WARNING: The DC power plant is supplied from a nominal high voltage AC voltage source. Keep the AC input enclosure cover in place when the system is operational or energized
1.Verify that AC voltage is present for each rectifier at the back- plane position (Blue J2 of
2.Verify that all of the circuit breaker positions are labeled to the corresponding rectifier correctly.
3.Insert all rectifiers.
4.Turn all rectifier circuit breakers on.
5.The main screen should appear on the control unit display (see Figure
NOTE: When AC power is initially applied, there is a
MX28B1200/2400 MX28B1200/4800 | Page 28 |