APC BC300 Series manual UPS Model Input Output Recom DC Voltage DC Current Mended, Mib

Page 17

Installation

UPS Model

 

Input

 

Output

 

Recom-

 

DC Voltage

 

DC Current

 

 

 

 

Current

 

Current

 

mended

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

MIB

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

40kW 208V

161A

111A

200AT

216V

200A

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

40 kW 450V

 

75A

 

51A

 

95AT

 

216V

 

200A

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

40kW 480V

 

69A

 

48A

 

130AT

 

216V

 

200A

 

Notes:

1.3- or 4-wire provided source.

2.Cables not provided by APC.

3.Recommended input over-current protection (MIB) based on an 80% rated device.

4.All AC cables must be AC 3- or 4-wire 3-phase.

5.Keep UPS input, output and control cables in separate conduits.

6.Installation must comply with all applicable national and local codes.

NOTICE!

Over-current protection and UPS input AC disconnect means must be provided.

See the “Technical Specifications” section in this Installation Guide for recommended UPS input and output over-current protection.

CAUTION!

UPS systems can be connected as 3-phase, a 3-wire plus ground, provided that the load is not connected to the neutral conductor.

NOTICE!

Only authorized electricians may install the UPS and all applicable codes must be observed.

NOTICE!

Always keep AC, DC and communication cables separated.

NOTICE!

The grounding electrode conductor (Protective Earth - PE) must be the same size (ampacity) as the UPS input circuit conductors. Conduit is not an acceptable grounding electrode conductor - see National Electrical Code Section 250-91(a).

NOTICE!

The unit is wired from the factory as a separately derived system. Output neutral is bonded to equipment ground through main bonding jumper inside the UPS. See National Electrical Code Article 250-5(d) and 250-26 for correct installation grounding.

NOTICE!

The maintenance bypass switch must be a 4-pole device switching all three phases and neutral. If you are using a 3-pole device, contact APC Technical Support for instructions on how to convert the unit to a not-separately derived system.

 

990-1401

 

 

Installation Guide APC BC300 Series 40kW 208/450/480V UPS

17

Image 17
Contents Copyright 2002 APC Denmark ApS APC BC300 Series 40kW 208/450/480V Installation GuideThank You Installation Guide APC BC300 Series 40kW 208/450/480V UPSSafety Symbols used in this manual Contents Introduction IntroductionTools and Equipment Needed Insulated Tools and Other Equipment NeededPlease Recycle Receiving, Unpacking and Moving to SiteRequirements on Site InstallationInstallation Insulated and other tools required Installing the Conduit Connection KitUPS Footprint measurements in inches & mm Footprint Installing Conduit Box and Base Covers Conduit Connection Kit ContentsInstalling Pedestals Installing the Maintenance Bypass Panel and UPS SBP Electrical Schematic Component Overview Component Overview door openWire Terminals Wire TerminalsUtility input Wiring Diagram for BC300Single Line Diagram Single Line Diagram for BC300Single Line Diagram 40kW 69A MIB UPS Model Input Output Recom DC Voltage DC Current MendedExternal Connection Board External Connection BoardCommunication Interface Board Communication Interface Board OptionCommunication Interface Smart Slot and Connection of Triple ChassisAPC BC300 Triple Chassis Safety WarningsProduct Description Monitoring PortInstalling Management Products Power InputInstalling Management Cards To UPS PortPowering the APC BC300 Triple Chassis Cascading setup of the APC BC300 Triple ChassisPower Considerations Power AdaptersDetermining Power Requirements Triple Chassis Power ConsiderationsTroubleshooting Problem Possible Cause SolutionProduct Specifications Monitoring Port Pin Assignments Monitoring Port Pin Assignment Power, Physical, and Environmental Specifications Installation of External Batteries and Battery BreakerBattery Installation PhysicalBattery Installation Guidelines Do not connect the negative cables to the UPS yet Battery Replacement Initial Start-up and Phase Check External Batteries Initial Start-up and Phase CheckInitial Start-up and Phase Check Clearing the Events Log Clearing the Events LogStart-up and Shutdown Procedure Start-up and Shutdown ProcedureStart-up from Maintenance Bypass Shutdown ProcedureIf you have shut the loads down Move on to step APC BC300 Series 40 kW Technical Data Technical SpecificationsTechnical Specifications Dimensions/Weight Battery SpecificationsHow to Contact APC How to Contact APCAPC Corporate Fairgrounds Road West Kingston, RIHow to Contact APC