5.0 Clearing the Events Log

The events log contains the 250 most recent UPS events, including alarms. To clear the events log, follow the steps below:

1.Press and at the same time. The display should show “Key in password”.

2.Using the key pad, enter “920701”. The display should show “Logging stack is reset”. The events log is now cleared.

3.Press . The display should show “Normal operation load power xx%”.

If the unit will not be in operation immediately, go to the “Start-up and Shutdown Procedure” section.

990-1401

32

Installation Guide APC BC300 Series 40kW 208/450/480V UPS

Image 32
Contents APC BC300 Series 40kW 208/450/480V Installation Guide Copyright 2002 APC Denmark ApSThank You Installation Guide APC BC300 Series 40kW 208/450/480V UPSSafety Symbols used in this manual Contents Introduction IntroductionTools and Equipment Needed Insulated Tools and Other Equipment NeededReceiving, Unpacking and Moving to Site Please RecycleRequirements on Site InstallationInstallation Insulated and other tools required Installing the Conduit Connection KitUPS Footprint measurements in inches & mm Footprint Installing Conduit Box and Base Covers Conduit Connection Kit ContentsInstalling Pedestals Installing the Maintenance Bypass Panel and UPS SBP Electrical Schematic Component Overview door open Component OverviewWire Terminals Wire TerminalsWiring Diagram for BC300 Utility inputSingle Line Diagram for BC300 Single Line DiagramSingle Line Diagram 40kW 69A UPS Model Input Output Recom DC Voltage DC Current Mended MIBExternal Connection Board External Connection BoardCommunication Interface Board Option Communication Interface BoardSmart Slot and Connection of Triple Chassis Communication InterfaceSafety Warnings APC BC300 Triple ChassisProduct Description Monitoring PortPower Input Installing Management ProductsInstalling Management Cards To UPS PortCascading setup of the APC BC300 Triple Chassis Powering the APC BC300 Triple ChassisPower Considerations Power AdaptersTriple Chassis Power Considerations Determining Power RequirementsTroubleshooting Problem Possible Cause SolutionProduct Specifications Monitoring Port Pin Assignments Monitoring Port Pin Assignment Installation of External Batteries and Battery Breaker Power, Physical, and Environmental SpecificationsBattery Installation PhysicalBattery Installation Guidelines Do not connect the negative cables to the UPS yet Battery Replacement Initial Start-up and Phase Check External Batteries Initial Start-up and Phase CheckInitial Start-up and Phase Check Clearing the Events Log Clearing the Events LogStart-up and Shutdown Procedure Start-up and Shutdown ProcedureStart-up from Maintenance Bypass Shutdown ProcedureIf you have shut the loads down Move on to step APC BC300 Series 40 kW Technical Data Technical SpecificationsTechnical Specifications Battery Specifications Dimensions/WeightHow to Contact APC How to Contact APCAPC Corporate Fairgrounds Road West Kingston, RIHow to Contact APC