APC BC300 Series manual Conduit Connection Kit Contents, Installing Pedestals

Page 8

Installation

3.2.1 Conduit Connection Kit Contents

For Pedestals:

23 pedestals

4 M8 x 100 mm bolts

4 M8 lock washers

4 M8 flat washers

4 M8 nuts

For Conduit Box:

1 Conduit Box

1 Conduit Box Cover

11 M5 x 12 mm T20 Torx screws

11 M5 lock washers

11 M5 flat washers

For Base Covers:

2 Side Base Covers

2 Front/Rear Base Covers

Hook and loop fasteners

3.2.2Installing Pedestals

CAUTION!

Heavy Equipment. Use caution and appropriate equipment to safely lift the UPS several inches above the floor when installing pedestals.

1)Remove brackets mounted to the UPS feet during shipping

2)Lift the UPS off the floor and place the pedestals under UPS feet where the holes of pedestals and holes in UPS feet are aligned

3)With caution lower the UPS feet into pedestal

4)Fasten but DO NOT TIGHTEN bolts, washers and nuts on the four corner feet of UPS

NOTICE!

Place flat washer under the bolt head and the lock washer under the nut.

5)Move the UPS to the installation site

6)Tighten the bolts

3.2.3 Installing Conduit Box and Base Covers

1)Punch conduit holes in the back of the conduit box

2)Place the conduit box between the center leg and right leg of the unit, with the open side facing the front of the unit

990-1401

8

Installation Guide APC BC300 Series 40kW 208/450/480V UPS

Image 8 Contents
APC BC300 Series 40kW 208/450/480V Installation Guide Copyright 2002 APC Denmark ApSThank You Installation Guide APC BC300 Series 40kW 208/450/480V UPSSafety Symbols used in this manual Contents Introduction IntroductionTools and Equipment Needed Insulated Tools and Other Equipment NeededReceiving, Unpacking and Moving to Site Please RecycleRequirements on Site InstallationInstallation Insulated and other tools required Installing the Conduit Connection KitUPS Footprint measurements in inches & mm Footprint Installing Conduit Box and Base Covers Conduit Connection Kit ContentsInstalling Pedestals Installing the Maintenance Bypass Panel and UPS SBP Electrical Schematic Component Overview door open Component OverviewWire Terminals Wire TerminalsWiring Diagram for BC300 Utility inputSingle Line Diagram for BC300 Single Line DiagramSingle Line Diagram 40kW 69A UPS Model Input Output Recom DC Voltage DC Current Mended MIBExternal Connection Board External Connection BoardCommunication Interface Board Option Communication Interface BoardSmart Slot and Connection of Triple Chassis Communication InterfaceSafety Warnings APC BC300 Triple ChassisProduct Description Monitoring PortPower Input Installing Management ProductsInstalling Management Cards To UPS PortCascading setup of the APC BC300 Triple Chassis Powering the APC BC300 Triple ChassisPower Considerations Power AdaptersTriple Chassis Power Considerations Determining Power RequirementsTroubleshooting Problem Possible Cause SolutionProduct Specifications Monitoring Port Pin Assignments Monitoring Port Pin Assignment Installation of External Batteries and Battery Breaker Power, Physical, and Environmental SpecificationsBattery Installation PhysicalBattery Installation Guidelines Do not connect the negative cables to the UPS yet Battery Replacement Initial Start-up and Phase Check External Batteries Initial Start-up and Phase CheckInitial Start-up and Phase Check Clearing the Events Log Clearing the Events LogStart-up and Shutdown Procedure Start-up and Shutdown ProcedureStart-up from Maintenance Bypass Shutdown ProcedureIf you have shut the loads down Move on to step APC BC300 Series 40 kW Technical Data Technical SpecificationsTechnical Specifications Battery Specifications Dimensions/WeightHow to Contact APC How to Contact APCAPC Corporate Fairgrounds Road West Kingston, RIHow to Contact APC
Related manuals
Manual 38 pages 11.26 Kb