APC BC300 Series manual Battery Replacement

Page 30

Installation

3.6.2 Battery Replacement

Only authorized service personnel familiar with battery systems may replace batteries. See the “Start-up & Shutdown Procedure” section in this Installation Guide to bypass and shut down the UPS.

CAUTION!

Study all warnings at the beginning of this section before replacing the batteries.

Use the Same Battery Number and Type: To ensure a well-functioning UPS and to maintain proper battery charger operation, you must replace a given number of batteries with the same number of batteries. The batteries must be the same manufacturer type as the original batteries and have the same voltage and ampere- hour rating as the original batteries.

Verify that the Battery Terminal is not Grounded: If any battery terminal is inadvertently grounded, you must remove the connection from the terminal to ground (earth) before you service the batteries. Contacting any part of a grounded battery can cause a risk of electric shock. To reduce the risk of electric shocks, disconnect the ground connection before you service the batteries.

Handle Used Batteries with Care: Assume that old batteries are fully charged. Use the same precautions you would use when handling a new battery. Do not short battery terminals or the battery string with a cable or tool when you disconnect the batteries.

Dispose of Batteries Properly: Do not dispose of batteries in a fire as the batteries may explode. Do not open or mutilate batteries. Released electrolyte is harmful to the skin and eyes and may be toxic. Batteries contain lead. Many state and local governments have regulations about disposing of used batteries. For assistance, call APC Technical Support or call your local APC office.

990-1401

30

Installation Guide APC BC300 Series 40kW 208/450/480V UPS

Image 30
Contents APC BC300 Series 40kW 208/450/480V Installation Guide Copyright 2002 APC Denmark ApSInstallation Guide APC BC300 Series 40kW 208/450/480V UPS Safety Symbols used in this manualThank You Contents Tools and Equipment Needed IntroductionIntroduction Insulated Tools and Other Equipment NeededReceiving, Unpacking and Moving to Site Please RecycleInstallation InstallationRequirements on Site Installing the Conduit Connection Kit UPS Footprint measurements in inches & mm FootprintInsulated and other tools required Conduit Connection Kit Contents Installing PedestalsInstalling Conduit Box and Base Covers Installing the Maintenance Bypass Panel and UPS SBP Electrical Schematic Component Overview door open Component OverviewWire Terminals Wire TerminalsWiring Diagram for BC300 Utility inputSingle Line Diagram for BC300 Single Line DiagramSingle Line Diagram 40kW 69A UPS Model Input Output Recom DC Voltage DC Current Mended MIBExternal Connection Board External Connection BoardCommunication Interface Board Option Communication Interface BoardSmart Slot and Connection of Triple Chassis Communication InterfaceProduct Description Safety WarningsAPC BC300 Triple Chassis Monitoring PortInstalling Management Cards Power InputInstalling Management Products To UPS PortPower Considerations Cascading setup of the APC BC300 Triple ChassisPowering the APC BC300 Triple Chassis Power AdaptersTroubleshooting Triple Chassis Power ConsiderationsDetermining Power Requirements Problem Possible Cause SolutionProduct Specifications Monitoring Port Pin Assignments Monitoring Port Pin Assignment Battery Installation Installation of External Batteries and Battery BreakerPower, Physical, and Environmental Specifications PhysicalBattery Installation Guidelines Do not connect the negative cables to the UPS yet Battery Replacement Initial Start-up and Phase Check Initial Start-up and Phase CheckInitial Start-up and Phase Check External Batteries Clearing the Events Log Clearing the Events LogStart-up from Maintenance Bypass Start-up and Shutdown ProcedureStart-up and Shutdown Procedure Shutdown ProcedureIf you have shut the loads down Move on to step Technical Specifications Technical SpecificationsAPC BC300 Series 40 kW Technical Data Battery Specifications Dimensions/WeightAPC Corporate How to Contact APCHow to Contact APC Fairgrounds Road West Kingston, RIHow to Contact APC