APC BC300 Series manual Installing the Maintenance Bypass Panel and UPS

Page 9

Installation

3) Use four T20 torx screws and washers to fasten the conduit box to the front legs of the UPS

NOTICE!

Place flat washer, lock washer and screw in this particular order.

4)After all UPS wiring has been completed, attach conduit box cover to the front of the conduit box

5)Use hook and loop fasteners to attach the base covers to the UPS

3.3Installing the Maintenance Bypass Panel and UPS

IMPORTANT!

If you do not have an APC Maintenance Bypass Panel, you must provide overcurrent protection and a UPS input AC disconnect means.

APC strongly recommends that a means of bypassing the UPS from the critical load be provided for maintenance.

Follow these guidelines when installing the Maintenance Bypass Panel and UPS:

Install the Maintenance Bypass Panel within sight of the UPS. When installing the Maintenance Bypass Panel, see illustrations under Wiring Diagram for BC300 and any instructions provided with the Maintenance Bypass Panel.

Install all wiring in accordance with applicable electrical codes. Use 75° C copper conductors.

Install the AC input and UPS output in separate conduits. UPS output circuits must be installed in dedicated conduit systems and separate from other electrical circuits.

Control wiring must be installed in a separate conduit.

Good ground connections are necessary to reduce electrical noise and make the operation of the UPS and the loads safe. Follow the grounding guidelines in the installation wiring diagram. Refer to the National Electrical Code (NEC), appropriate IEEE documents, and all applicable codes.

For systems with non-linear, neutral-connected loads, standard practice is to size the neutral conductor for 1.732 times the phase current.

When installing the AC wiring, refer to the illustration Single Line Diagram for BC300 and to any additional diagrams provided with the UPS. The illustration shows typical installations. Your installation may be different.

See Component Overview illustration for a view of the UPS with covers removed. See Wiring Termination or Component Overview illustrations for UPS wiring terminations. Refer to illustration External Connection Board for information on the external connection board. See illustration Communication Interface Board (Option) for information on the optional communication interface board.

If you have any questions, contact APC Technical Support for assistance.

 

990-1401

 

 

Installation Guide APC BC300 Series 40kW 208/450/480V UPS

9

Image 9
Contents Copyright 2002 APC Denmark ApS APC BC300 Series 40kW 208/450/480V Installation GuideInstallation Guide APC BC300 Series 40kW 208/450/480V UPS Safety Symbols used in this manualThank You Contents Introduction IntroductionTools and Equipment Needed Insulated Tools and Other Equipment NeededPlease Recycle Receiving, Unpacking and Moving to SiteInstallation InstallationRequirements on Site Installing the Conduit Connection Kit UPS Footprint measurements in inches & mm FootprintInsulated and other tools required Conduit Connection Kit Contents Installing PedestalsInstalling Conduit Box and Base Covers Installing the Maintenance Bypass Panel and UPS SBP Electrical Schematic Component Overview Component Overview door openWire Terminals Wire TerminalsUtility input Wiring Diagram for BC300Single Line Diagram Single Line Diagram for BC300Single Line Diagram 40kW 69A MIB UPS Model Input Output Recom DC Voltage DC Current MendedExternal Connection Board External Connection BoardCommunication Interface Board Communication Interface Board OptionCommunication Interface Smart Slot and Connection of Triple ChassisAPC BC300 Triple Chassis Safety WarningsProduct Description Monitoring PortInstalling Management Products Power InputInstalling Management Cards To UPS PortPowering the APC BC300 Triple Chassis Cascading setup of the APC BC300 Triple ChassisPower Considerations Power AdaptersDetermining Power Requirements Triple Chassis Power ConsiderationsTroubleshooting Problem Possible Cause SolutionProduct Specifications Monitoring Port Pin Assignments Monitoring Port Pin Assignment Power, Physical, and Environmental Specifications Installation of External Batteries and Battery BreakerBattery Installation PhysicalBattery Installation Guidelines Do not connect the negative cables to the UPS yet Battery Replacement Initial Start-up and Phase Check Initial Start-up and Phase CheckInitial Start-up and Phase Check External Batteries Clearing the Events Log Clearing the Events LogStart-up and Shutdown Procedure Start-up and Shutdown ProcedureStart-up from Maintenance Bypass Shutdown ProcedureIf you have shut the loads down Move on to step Technical Specifications Technical SpecificationsAPC BC300 Series 40 kW Technical Data Dimensions/Weight Battery SpecificationsHow to Contact APC How to Contact APCAPC Corporate Fairgrounds Road West Kingston, RIHow to Contact APC