APC BC300 Series manual Receiving, Unpacking and Moving to Site, Please Recycle

Page 5

Receiving, Unpacking, Moving and Storing the UPS and Batteries

2.0Receiving, Unpacking, Moving and Storing the UPS and Batteries

2.1Receiving, Unpacking and Moving to Site

CAUTION!

Heavy equipment. To prevent personal injury or equipment damage, use caution when handling and transporting UPS cabinet and equipment.

1.While the UPS system is still on the truck, inspect the equipment and shipping container(s) for any signs of damage. Do not install the system if damage is apparent. If damage has occurred, notify APC as soon as possible.

2.Compare the shipment with the bill of lading. Report any missing items to the carrier and to APC immediately.

3.Remove the screws on the bottom part of the packaging side plates.

4.Remove the packing materials from the unit.

5.Verify compliance between type label on reverse side of UPS front door and system ordered. Check input and output voltage.

6.Unbolt the unit from the pallet.

7.Remove the unit from the pallet with a forklift.

8.Use a forklift or hand truck to transport the unit to the installation or storage site. Study the footprint to decide how to move the UPS through doorways and into position.

PLEASE RECYCLE

The shipping materials are recyclable. Please save for later use or dispose of them appropriately.

2.2Storing the UPS and Batteries

Store the APC BC300 Series UPS between -4 and 104° F (-20 and 40° C). However, APC recommends that the unit and batteries be stored between 59 and 77° F (15 and 25° C). This temperature range, or cooler, allows batteries a longer shelf life. Recharge stored batteries every 90 to 120 days.

See the section “Requirements on Site” in this Installation Guide for further details.

 

990-1401

 

 

Installation Guide APC BC300 Series 40kW 208/450/480V UPS

5

Image 5
Contents Copyright 2002 APC Denmark ApS APC BC300 Series 40kW 208/450/480V Installation GuideThank You Installation Guide APC BC300 Series 40kW 208/450/480V UPSSafety Symbols used in this manual Contents Introduction IntroductionTools and Equipment Needed Insulated Tools and Other Equipment NeededPlease Recycle Receiving, Unpacking and Moving to SiteRequirements on Site InstallationInstallation Insulated and other tools required Installing the Conduit Connection KitUPS Footprint measurements in inches & mm Footprint Installing Conduit Box and Base Covers Conduit Connection Kit ContentsInstalling Pedestals Installing the Maintenance Bypass Panel and UPS SBP Electrical Schematic Component Overview Component Overview door openWire Terminals Wire TerminalsUtility input Wiring Diagram for BC300Single Line Diagram Single Line Diagram for BC300Single Line Diagram 40kW 69A MIB UPS Model Input Output Recom DC Voltage DC Current MendedExternal Connection Board External Connection BoardCommunication Interface Board Communication Interface Board OptionCommunication Interface Smart Slot and Connection of Triple ChassisAPC BC300 Triple Chassis Safety WarningsProduct Description Monitoring PortInstalling Management Products Power InputInstalling Management Cards To UPS PortPowering the APC BC300 Triple Chassis Cascading setup of the APC BC300 Triple ChassisPower Considerations Power AdaptersDetermining Power Requirements Triple Chassis Power ConsiderationsTroubleshooting Problem Possible Cause SolutionProduct Specifications Monitoring Port Pin Assignments Monitoring Port Pin Assignment Power, Physical, and Environmental Specifications Installation of External Batteries and Battery BreakerBattery Installation PhysicalBattery Installation Guidelines Do not connect the negative cables to the UPS yet Battery Replacement Initial Start-up and Phase Check External Batteries Initial Start-up and Phase CheckInitial Start-up and Phase Check Clearing the Events Log Clearing the Events LogStart-up and Shutdown Procedure Start-up and Shutdown ProcedureStart-up from Maintenance Bypass Shutdown ProcedureIf you have shut the loads down Move on to step APC BC300 Series 40 kW Technical Data Technical SpecificationsTechnical Specifications Dimensions/Weight Battery SpecificationsHow to Contact APC How to Contact APCAPC Corporate Fairgrounds Road West Kingston, RIHow to Contact APC