APC BC300 Series manual Initial Start-up and Phase Check

Page 31

Initial Start-up and Phase Check

4.0 Initial Start-up and Phase Check

After installing the unit, use this section to perform the initial start-up and the phase check for the Maintenance Bypass Panel.

4.1Initial Start-up and Phase Check (External Batteries)

1.Ensure that the external battery breaker for the battery system is set to “OFF”.

2.Turn the pre-charge/discharge switch to the “pre-charge” position and hold it until the LED turns off.

3.Switch the battery breaker “ON”. The UPS display should show “System type xxkVA xxxV”.

4.Within 20 seconds, the display should show **Stand-by** and an audible alarm should sound.

5.At utility input, switch on the input power to the Maintenance Bypass Panel.

6.At the Maintenance Bypass Panel, switch the UPS AC disconnect switch “ON”.

7.Check the phase rotation at the service panel and the unit. The unit will not start if the phase rotation is incorrect. The phase rotation must be A, B, C and clockwise.

8.When the audible alarm stops, press the green “ON” button located inside the UPS front door. The display will show “Normal operation load power xx%”.

NOTICE!

One or more alarms may occur. If the alarm(s) persists for more than 20 seconds, refer to the “Alarms” section of the User Guide. If the unit activates a “battery monitor alarm”, you should set the user parameter “battery monitor reset” to “ON”.

990-1401

Installation Guide APC BC300 Series 40kW 208/450/480V UPS

31

Image 31 Contents
Copyright 2002 APC Denmark ApS APC BC300 Series 40kW 208/450/480V Installation GuideSafety Symbols used in this manual Installation Guide APC BC300 Series 40kW 208/450/480V UPSThank You Contents Insulated Tools and Other Equipment Needed IntroductionIntroduction Tools and Equipment NeededPlease Recycle Receiving, Unpacking and Moving to SiteInstallation InstallationRequirements on Site UPS Footprint measurements in inches & mm Footprint Installing the Conduit Connection KitInsulated and other tools required Installing Pedestals Conduit Connection Kit ContentsInstalling Conduit Box and Base Covers Installing the Maintenance Bypass Panel and UPS SBP Electrical Schematic Component Overview Component Overview door openWire Terminals Wire TerminalsUtility input Wiring Diagram for BC300Single Line Diagram Single Line Diagram for BC300Single Line Diagram 40kW 69A MIB UPS Model Input Output Recom DC Voltage DC Current MendedExternal Connection Board External Connection BoardCommunication Interface Board Communication Interface Board OptionCommunication Interface Smart Slot and Connection of Triple ChassisMonitoring Port Safety WarningsAPC BC300 Triple Chassis Product DescriptionTo UPS Port Power InputInstalling Management Products Installing Management CardsPower Adapters Cascading setup of the APC BC300 Triple ChassisPowering the APC BC300 Triple Chassis Power ConsiderationsProblem Possible Cause Solution Triple Chassis Power ConsiderationsDetermining Power Requirements TroubleshootingProduct Specifications Monitoring Port Pin Assignments Monitoring Port Pin Assignment Physical Installation of External Batteries and Battery BreakerPower, Physical, and Environmental Specifications Battery InstallationBattery Installation Guidelines Do not connect the negative cables to the UPS yet Battery Replacement Initial Start-up and Phase Check Initial Start-up and Phase CheckInitial Start-up and Phase Check External Batteries Clearing the Events Log Clearing the Events LogShutdown Procedure Start-up and Shutdown ProcedureStart-up and Shutdown Procedure Start-up from Maintenance BypassIf you have shut the loads down Move on to step Technical Specifications Technical SpecificationsAPC BC300 Series 40 kW Technical Data Dimensions/Weight Battery SpecificationsFairgrounds Road West Kingston, RI How to Contact APCHow to Contact APC APC CorporateHow to Contact APC
Related manuals
Manual 38 pages 11.26 Kb