Sterling SGFE operating instructions Vacuum generator

Page 38

Vacuum generator

5.6. Vacuum generator

»

L

F

&

SM4-618

Explosive gases and mixtures of gas and air must not be con- veyed.

Solid particles and dust must be separated before entry to the vacuum generator.

For all work on the equipment, hearing protection should be worn.

Avoids impairment of hearing!

The manufacturer’s operating instructions should be followed.

An acoustic cover should be installed when vacuum genera- tors are located in work rooms.

When installing an acoustic cover, care should be taken that the ventilation of the eletric motors is not impeded.

Examples for the expected noise level: side vane vacuum pump GSV

2.2 kW:

approx. 72 dB (A)

4.0 kW:

approx. 75 dB (A)

rotary value pump GDS

 

7.5 kW:

approx. 75 dB (A)

11.0 kW:

approx. 77 dB (A)

rotary lobe vacuum pump GDK

4.0 kW:

approx. 78 dB(A)

Assembly instructions 5-5

Image 38
Contents Sterling Material Processing Parts and Service Department Technical service Edition 10/01Sgfe Table of contents Functional description Assembly instructionsTechnical data Spare parts list Accessories Electrical manualSafety instructions GeneralFor your safety For your safety General For your safety Assembly For your safety Operation For the operating safety of the equipment Concerning these Operating Instructions General InformationConcerning these Operating Instructions Explanations and Definitions Concerning these Operating Instructions Start-up Control system Switching on the control system Key assignment Switching on the control systemChanges only after consultation with Sterling Service Setting the basic parametersSignal times flap B01 Emptying time B14 Setting the basic parameters Conveying time B05Line clearing B09 Setting the basic parameters Blower run on time B17 Error tolerance B22Starting the conveying procedure First conveying operationsViewing Alarm Messages Possible events Fault hopperSwitching off the unit Maintenance General Maintenance schedule Maintenance schedule Checking the direction of rotation of the vacuum generator Testing the conduit system If the conditions points 3 + 4 are fulfilled Adjusting the suction tubeIf conditions points 3 + 4 are not fulfilled Cleaning/replacing the filter cartridge RespServicing the accessories Assembly instructions Material feed InstallationTransport Suction pipe Pipework Vacuum generator Installing the accessories Rotary lobe vacuum pump GDKElectrical connection Functional description General Technical data Technical dataDimension sheet Sgfe Dimension sheet GDK 4 kW Dimension sheet GSVDimension sheet GDS Spare parts list Pos ID-No Designation OptionalAccessories Electrical manual