Nordyne AND M5S, SERIES M1B Oil Tank and Piping Installation, Fuel line Hook-Up

Page 17

For L.P. gas, pressure to the gas valve must be more than 11” W.C. but not more than 13” W.C. Pressure is reduced to 10” W.C. by the pressure regulator in the gas valve.

CAUTION:

Furnace conversion must be per- formed by a qualified technician. Improper conversion can cause unsafe operation, explosion, fire and/or asphyxiation.

Oil Tank and Piping Installation

The following procedures are recommended as good practice. However, requirements of local codes and ordinances, H.U.D. Manufactured Home and Safety Standards or National Fire Protection Association must be satisfi ed, where they apply, for an approved installation.

Use a tank capacity suitable for the application with a weatherproof, capped fi ll opening and a shielded vent to let in air as fuel is used.

The inside of the tank must be clean before fi lling. All water, rust, sediment, and debris must be fl ushed out.

A fuel or tank gauge (Figure 27) is recom- mended for easy checking of the fuel level. Check the gauge reading with a dipstick.

Locate the storage tank conveniently near the home. If the fuel tank is installed above ground, the tank may rest 3 to 4 inches off the ground. Fuel tanks may also be buried if properly coated to resist corrosion.The vertical dimension from the bottom of the fuel tank to the fuel pump must not exceed 10 feet.

Keep the tank fi lled, especially in the summer to reduce the accumulation of condensation.

One Line System

The one line system is highly recommended where vertical lift, from bottom of tank to pump, is less than eight feet (Figure 27). A single line hookup has the advantage of lower cost and quieter operation.

Two Line System

If a two pipe system is used or if oil is taken from the bottom of the tank, a fi lter is recommended. A two line system should only be used if vertical lift exceeds 8 feet.

1.Install the oil feed line as outlined in steps 1 - 6 below.

2.Install the oil pump bypass plug in the bottom return port.

3.Route the return line up through the furnace base to the return port of the pump. Route the other end of the line to the tank, using 3/8” O.D. copper tubing or 1/4” pipe with the ends capped.

4.Insert the return line through the second opening in the duplex bushing. If the bottom of the tank is lower than the pump intake, the tube should be inserted three or four inches from the tank bottom. If the bottom of the tank is higher than the pump intake, the return line should extend not more than 8” inside the tank.

Fuel line Hook-Up

1.Use a 3/8” O.D. copper tubing for the fuel line. NOTE: Cap the end with tape to keep out dirt while the line is being routed.

2.Install duplex bushing for two 3/8” lines in the top fi tting of the tank. See Figure 27.

3.Insert one end of the tubing through the duplex bushing until it is three to fi ve inches from the bottom drain. Tighten the bushing.

4.Route the line where it will not incur any damage. Make bends gradual and avoid kinks which might restrict oil fl ow.

Bypass Solenoid Valve

Nozzle Port

3/16 Flare Fitting

Cordset

Pressure Adjustment

Screw

3/8" Oil Supply Line

 

 

Oil

Flue Gas

Vent with cap

 

 

 

Furnace

2" Duplex

 

 

Sampling

 

 

 

 

Gauge

Bushing

 

 

 

Hole

 

 

 

 

 

 

2" Fill

Top of Tank

 

 

 

 

 

 

 

 

On-Off-Fan

 

 

 

 

 

Switch

 

Shut-off

 

 

 

Guide

 

Valve

8 ft.

 

 

Pipe

 

 

Control

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Panel

 

 

Drain

 

 

 

Oil-Gun

End of Oil Supply Line

 

Optional

 

 

 

Alternate

 

Burner

3" to 5" Above Bottom Drain

 

Fuel

 

 

Fuel Line

 

 

 

 

Filter

 

Floor

 

 

Entry

 

 

 

 

 

 

NOTE: Additional venting may be

 

 

 

Floor Cavity

required if tank is filled rapidly.

 

 

 

 

 

Beckett

Inlet Port

 

A2EA-6520

1/4 NPTF

4

GPH 100-150 PSI 3450 RPM

 

NO. 2 & LIGHTER FUEL

 

3 GPH 150-200 PSI 3450 RPM

 

 

 

Bleed & Gauge Port

Inlet Port

 

Return Port - Install 1/6” Bypass Pipe

1/4 NPTF

 

Plug for 2-pipe System Only.

 

 

(Use 5/32” Allen Wrench)

If fuel pump fails to lift oil, check for air leaks and tighten all fuel fittings. Re- prime fuel pump by injecting fuel oil into optional (top) return port. Replace return port plug and repeat priming procedure.

Figure 27. Typical Oil Piping for Above Ground (Single-Line) Supply

17

Image 17
Contents For installation Installation InstructionsStanding Pilot Models Direct Ignition Models Oil Gun Models Homeowner Information Installer Information InformationReturn Air Connections Supply Air Connections Requirements and Codes Safety InformationGeneral Installation Gas Piping and Gas Pipe Pressure TestingSafety Combustion and Ventilation AirALL Models Closet Alcove General InformationMinimum Clearances Applications AssemblyUnit Location BlowerReturn Air Connections Circulating AIR RequirementsGas piping is not run in or through the return duct system Supply Air ConnectionsDetermine which duct connector to use from Furnace InstallationGeneral Information Requirements and CodesDuct Connector Sizes Standard Duct Connector Installation Cut-Out Dimensions for Standard Duct ConnectorsInstalling The Furnace Duct Connector TabsRequired ceiling and roof cut-out openings see Roof Jack InstallationRoof Jack Selection Application NotesSlant Deck Flashings Roof Jack Series If Roof Pitch is Slant Deck FactorInstallation of Transit-Mode Venting System Installing The Roof JackConnect fl ue pipe to fl ue collar of furnace. See Figure Secure fl ashing with appropriate fastenersElectrical Information Line Voltage WiringWire Heating Heating/Cooling Low Voltage WiringThermostat Wire Gauge Thermostat Length Unit to T’STATImportant Notes Fuel Supply and PipingFuel line Hook-Up Oil Tank and Piping InstallationConversion to Propane LP Gas Leak CheckFuel Oil Type Honeywell Gas Valve High Altitude ConversionStanding Pilot Valve Lighting Instructions Standing Pilot ModelsOperating Instructions for Direct Ignition Models M1M Replace the furnace doorPilot Flame Standing Pilot Only Burner AdjustmentsFor oil, shut off all valves Replace the furnace door Combustion Air Factory Combustion Air SettingsElectrode Setting Oil Gun Only Standing Pilot Operating SequenceStanding Pilot w/Induced Draft Blowers M1M Models with Direct IgnitionFurnace Controls & Functions Direct Ignition Furnaces Including Gas Gun M1B Series see , TroubleshootingStanding Pilot Models Page Optional Accessories Burner will not start and the LED indicator isCad Cell Resistance when Sensing flame Cad cell is operational, replace the primary controlRed LED Indicator Status Control Module Status Indicators M1M SeriesControl Module Status Indicator M1B Control Module Status Indicator M5S SeriesInstaller Information MaintenanceAdditional Oil Furnace Maintenance Clean or replace the oil fi lter element at the oil tankM1GB Burner Direct Blower TonsM1MC Manifold Pressure Natural Gas 3.5 w.cOrifi ce Size Nat. Gas Orifi ce Size LP Equivalent Orifice Sizes for High Altitude InstallationsOutput Mbtuh Orifi ce Size Nat. GasGas Flow Rates Cubic Feet per Hour GAS InformationModels Wiring DiagramsM1GH 077, 090 Models M1GB 056, 070 Models Gas AtmosphericWiring Diagram Steady OFF No power Blinking Wiring Diagram Installation Address Installation / Performance Check List