Vermont Casting RADVTCMB, RADVTMB, RADVTSG, RADVTCB Install the Optional Fan, Remove rear shroud

Page 15

WARNING

This appliance is equipped with a three-prong (grounded) plug for your protection against shock hazard and should be plugged directly into a properly grounded three-prong receptacle. Do not cut or remove the grounding prong from this plug.

Install the Optional Fan

If you are installing the optional convection Fan Kit #2767 (FK26), continue here. It is easiest to install fan kit before connecting gas line. If you are not installing a Fan Kit, go to Page 16, Venting System Assembly.

1.The fan kit includes a Blower Assembly and a Rheo- stat Assembly, connected by a cable. (Fig. 15) The Blower Assembly mounts to the bottom rear of the stove, and the Rheostat mounts to the valve cover- plate. The assembly includes a ‘snapstat’ which au- tomatically turns the fan On (or Off) above (or below) approximately 109˚. The Rheostat also provides a range of fan speed settings from Off (which overrides the snapstat function) to High. Unpack and inspect the Blower assembly. Confirm that the fan spins freely.

 

Not Used On

Snapstat

 

RF Models

Bracket

Not

 

Snapstat/

 

Extension

Used On

Assembly

Radiance

 

 

 

Rheostat

 

 

Assembly

 

 

Not Used

 

 

On RF

 

 

Models

Blower

 

 

Assembly

Connect to PC board on

 

 

ST473

 

RF models only

 

 

Fig. 15

Fan kit components.

 

2.Remove the rear shroud panel (Fig. 17) and fasten the blower assembly to the firebox back with the two bolts provided. (Fig. 17)

NOTE: Steps 3 and 4 do not apply to RADVTC series Comfort Control models. On these models, after attaching blower assembly to the firebox, run the spliced female leads to the front of the stove and at- tach to back of Honeywell valve. (Page 33, Fig. 59)

3.Attach the snapstat assembly to the snapstat bracket with two sheet-metal screws. Attach the snapstat bracket to the side shield. (Fig. 17)

4.The rheostat control switch attaches to the left side of the valve bracket at the front of the stove. (Fig. 18)

Radiance Direct Vent Gas Heater

ST147

Fig. 16 Remove rear shroud.

Side Shield

Snapstat

Bolts

ST149

Fig. 17 Attach blower assembly and snapstat.

Remove retaining nut from shaft of rheostat. (if preinstalled)

Insert the rheostat through the hole in the back of the left side of the valve bracket, aligning the locator pin with the smaller hole in that bracket.

Thread the retaining nut onto the shaft of the rheostat, tightening with a wrench. Do not over- tighten.

Attach the control knob to the rheostat shaft.

Use the wire tie to secure the fan and rheostat wire harnesses together.

Rheostat

Rheostat

Retaining Collar

Rheostat Knob

ST347a

 

Fig. 18 Attach the fan rheostat.

20012697

15

Image 15
Contents Radiance Direct Vent Gas Heater Table of Contents Commonwealth of Massachusetts Installation & Operating InstructionsCenterline Dimensions Radiance Direct Vent Stove DimensionsDirect Vent System Only Installation RequirementsLocating The Stove Clearance RequirementsWall and Ceiling Clearances Parallel Installation Minimum Clearance and Flue CenterlineCorner Installation Minimum Clearance and Flue Centerline Wall Centerline from FloorHorizontal Termination Gas SpecificationsGas Inlet and Manifold Pressures High ElevationsExamples for Extended Run/Restrictor Plate Settings Restrictor Plate Adjustment For Extended Pipe RunsRestictor Plate is used on Direct Vent installations only Restrictor Plate AdjustmentLocation of Vent Termination Vent Termination ClearancesGeneral Venting Information Termination Location Canadian Installations1 US Installations2Termination Clearances Venting Requirements and Options Approved Vent System ComponentsMinimum Horizontal Vent Kit 2792 Nonadjustable Pipe Twist Lock 45-Degree Elbow CG Non-adjustable Pipe Twist Lock 12 18 Adjustable Pipe12 18 Adjustable Pipe Twist Lock 24 Straight Pipe CG Non-adjustable Pipe Twist Lock 48 Straight Pipe CGUnpack and Assemble Legs Assembly ProceduresParts Bag Contents Tools RequiredRemove rear shroud Install the Optional FanVenting System Assembly General Information Install the Vent Adapter PipeFor Canadian installations The venting system must Install Vent Adapter Pipe Side Wall Termination AssemblySelkirk Corporation Vent Components Measure the horizontal length CFM System 9³⁄₈ x 9³⁄₈ 240 x 240 mm Vertical Through the Roof Vent AssemblyVent Termination Below Grade Cut the openingSelkirk Direct-Temp Metalbestos Direct Vent System To Termination Vertical VentingHorizontal Venting Inlet End Outlet EndOffsets Adjustable Length AJSupporting DIRECT-TEMP Horizontal Support Fire StoppingBelow grade installation Vertical Installation Fig Minimum Height Above Roof Requirements Install Log Set2626 Burner Information Connect the Gas Supply LineOperation Pilot Radvtc Series Flame & Temperature AdjustmentFlame Characteristics SIT Pilot Radvt SeriesHoneywell To Turn Off Gas To HeaterSIT Nova 820 Millivolt Valve Troubleshooting the Gas Control System Radvt SeriesDelay Timer Mode Shut Off ProcedureTransmitter Operation Off Mode On Manual ModeDisable Thermostat Function Auto ModeFan Override During Auto Mode Change Between F/C Temperature UnitsLocal Path On Path Auto Path Conversion Precautions Conversion ProcedureFuel Conversion Instructions Pilot Orifice Conversion Pilot Type 1 SIT PilotPilot type 2 Honeywell Pilot All Models Burner Orifice ConversionConversion to LP Input BTU/h Air Shutter AdjustmentInjector Orifice Size Matrix High Altitude OrificeMaintenance Gasket Replacement Inspect the Vent System AnnuallyCheck the Gas Flame Regularly Optional Thermostat Wiring DiagramsOn/Off Switch Wiring Schematic DiagramRadiance Direct Vent Gas Heater Description Radiance Direct Vent Gas HeaterFuel Conversion Kits Shell Enamel Parts Radiance Direct Vent Optional Accessories 4848 Radiance Direct Vent Gas Heater 5050 Limited Lifetime Warranty CFM Corporation