the assembled pipe to the appliance. Determine and mark the location of where the support collar will be at- tached to the pipe. Disconnect and remove assembled pipe. Attach the support collar per Step 10 (where marked) and reinstall assembly. This is due to limited space within the cathedral ceiling support box. Install any required offset supports.
11.Add lengths of pipe and firestop as necessary until assembly extends to a point above the roof which complies with local code requirements for minimum ter- mination height and with the appliance manufacturer’s installation instructions. (Fig. 45)
Radiance Direct Vent Gas Heater
NOTE: Whenever
12. Using a level, make sure the system is perfectly |
vertical. |
13. Slide the flashing, suitable for the roof pitch, down |
over the pipe protruding through the roof. Recheck |
orientation and use a silicone sealant around and under |
the perimeter of the flashing where it is in contact with |
the roof. Secure the flashing with roofing nails. Finish |
roofing around the pipe, covering the sides and upper |
ares of the flashing base with roofing material. How- |
ever, be sure the lower unnailed portion of the base |
| Minimum |
Roof Pitch | Height |
Flat to 7/12 | 1’0” |
Over 7/12 to 8/12 | 1’6” |
Over 8/12 to 8/12 | 2’0” |
Over 9/12 to 10/12 | 2’6” |
Over 10/12 to 11/12 | 3’3” |
Over 11/12 to 12/12 | 4’0” |
Over 12/12 to 14/12 | 5’0” |
Over 14/12 to 16/12 | 6’0” |
Over 16/12 to 18/12 | 7’0” |
Over 18/12 to 20/12 | 7’6” |
Over 20/12 to 21/12 | 8’0” |
Minimum Height
Above Roof
covers the roofing material. |
14. Position the storm collar around the pipe and slide |
down until it is in contact with the flashing. Secure the |
storm collar by inserting the two (2) tabs into the raised |
slots and fold tabs back. Seal the area between the |
storm collar and the vent pipe with a silicone sealant to |
prevent rain infiltration. |
15. Install the vertical termination (VC) by inserting it |
down into the top most section of pipe until it is fully |
seated. Depress lock tab to secure the cap to the pipe. |
NOTE: In high wind areas, it is recommended to screw |
termination to the pipe with two (2) #8 x 1/4” sheet |
metal screws. The screws should be approximately 3/4” |
from the bottom of the vertical termination’s galvanized |
collar. |
Fig. 45 Minimum Height Above Roof Requirements
Install Log Set
Before beginning log installation, remove stove front and glass frame. Refer to Figures 44 and 47.
1.Remove the logs from their packaging and inspect each piece for damage. DO NOT INSTALL DAM-
AGED LOGS.
ST139
Fig. 46 Remove the stove front.
ST141
Fig. 47 Release the latches to remove the glass frame.