All installations and services must be performed by qualified service personnel.
GROUND JOINT
MANUAL GAS
SHUT OFF VALVE
STREET ELBOW
GAS VALVE
18" N.P.T. MANIFOLD PRESSURE TAP
SEDIMENT TRAP
5 FT.
MHA1 SERIES
NOTE:
ACTUAL UNIT MAY
DIFFER SLIGHTLY FROM WHAT IS SHOWN.
Figure 6: Typical Gas Piping
1. INSTALLATION OF NATURAL GAS PIPING
The installation of the gas piping and the following test procedures must be performed by a qualified installer or service person.
The following chart may be used as a guide in sizing natural gas supply piping. The input loading of all gas appliances installed on any main or trunk line must be totaled to determine its required carrying capacity.
EXAMPLE: A line must supply a furnace of 100,000 BTU/hr input, a hot water heater of 40,000 BTU/hr input and gas range with a 30,000 BTU/hr input capacity. The total BTU/hr input loading on the line is 170,000 BTU/hr. The 200,000 BTU/hr column on the chart must be used in sizing the pipe.
23