Figure 12 – Vent Termination from Flat Roof 10' or Less from Parapet Wall

Provide a minimum clearance of 4 feet (1.2m) horizontally from electric meters, gas meters, regulators, and relief equipment. Never locate the vent cap above or below electric meters, gas meters, regulators, and relief equipment unless a 4 foot (1.2m) horizontal clearance is maintained.

Terminate the venting system at least 3 feet (0.9m) above any forced air inlet within 10 feet (3.05m).

Terminate the venting system at least 4 feet (1.2m) below, 4 feet (1.2m) beside, or 1 foot (30cm) above any door, window, or gravity air inlet into any building.

Locate vent termination at least 8 feet (2.4m) horizontally from any combustion air intake located above the sidewall termination cap.

￿CAUTION: Pool heaters which are shut down or will not operate may experience freezing due to convective air flow in the flue pipe, through the air inlet, or from negative pressure in the mechanical room. In cold climates, operate pump continuously to help prevent freezing of pool heater water. Provide proper freeze protection. See Freeze Protection, page 7.

TABLE–A

Figure 13 – Vent Termination from Flat Roof More Than 10' from Parapet Wall

Sidewall Vent Termination Clearances and Location

Locate the bottom of the vent terminal at least 12 inches (30cm) above grade and above normal snow levels. Locate the bottom of the vent terminal at least 7 feet (2.13m) above grade when located adjacent to public walkways. Do not terminate directly above a public walkway.

Do not terminate the venting system in a window well, stairwell, alcove, courtyard, or other recessed area. Do not terminate the venting system below grade.

Locate vent termination at least 3 feet (0.91m) from an inside corner of an L-shaped structure.

TABLE - B

Flue and Air Inlet Pipe Sizes

Input

Flue

Air Inlet

Btu/hr

Size

Size*

500,000

6"

6"

650,000

8"

8"

 

 

 

750,000

8"

8"

 

 

 

990,000

10"

10"

 

 

 

1,260,000

12"

12"

 

 

 

1,440,000

12"

12"

1,800,000

14"

12"

2,070,000

14"

12"

*Minimum diameter for air inlet pipe. Installer may increase diameter one pipe size for ease of installation, if needed. Refer to the National Fuel Gas Code (ANSI Z223.1) Vent Tables for additional guidance on vent sizing of fan assisted appliances.

11

Image 11
Contents GAS Heaters for Commercial Pool Applications Commercial Pool Heaters Unpacking General Product InformationCommercial Pool Heaters Product Identification Base for Combustible Floors Clearances from Combustible ConstructionCombustion Air Filter Freeze ProtectionCombustion Air Options InstallationCombustion Air from Interior Space Exhaust FansVertical Vent Termination Clearances and Location General InformationVenting Support Table B Sidewall Vent Termination Clearances and LocationSidewall Air Inlet Combustion Air Inlet PipingLength of Air Inlet Pipe Combined Air Inlet Points Vertical Rooftop Air InletNegative Draft Vent System OptionsConventional Negative Draft Venting Common Venting Systems Masonry Chimney InstallationsFlue Outlet Piping Inspection of a Masonry Chimney Vertical DirectAire VentingVenting of Flue Products Vent KitsSidewall Venting Sidewall Venting Without Fan Sidewall FanSidewall Venting Termination Masonry Chimney Installation TABLE-E Horizontal DirectAire VentingDirect Venting Combustion Air Inlet Piping Horizontal DV Venting TerminationFlue Pipe Materials Sealing Type-B Doublewall Vent Pipe or Galvanized Vent Pipe Length of Air Inlet PipeAir Inlet Piping Materials Vertical Rooftop Air Inlet Combined Combustion Air Inlet PointsOutdoor Vent/Air Inlet Location Outdoor Installation VentingOutdoor Vent Cap Kit Combustion Air Fan Adjustment for startup3-Way Valve Cover Installation Gas Pressure TestGas Train and Controls Connecting Gas Piping to the Pool HeaterGas Piping TABLE-J Combination Gas ValvesVenting of Combination Gas Valves Checking Gas Supply PressureTable K Multiple Unit Installations Gas Supply Pipe SizingMeasuring Net Manifold Gas Pressure Gas Manifold Pressure AdjustmentPumped Automatic Bypass Auxiliary Mixed Water Limit ControlWay Valve Cover Heater is Within 15 Feet of Pool Piping Heaters are within 15 feet Perpendicular of Pool Piping Automatic Chlorinator and Chemical Feeders Water Flow SwitchRelief Valve Way Automatic Bypass Valve Wiring Pump Purge Delay OptionService Indicator Option TABLE-M Terminal Strip Connection OptionsLighting Instructions OperationStarting the Filter System Pre-Start ChecklistTo Turn Off Gas To Pool Heater Operation Error Messages Displayed by the Temperature Controller Programming ModeIgnition Module Lockout Functions Diagnostic Status IndicationHot Surface Igniter and Ignition Control Module Hot Surface Ignition Control ModuleIgnition and Control Timings Access to Internal Control PanelTABLE-N TABLE-O Water ChemistryTest Recommended Level TABLE-PHeat Exchanger Pipe Size RequirementsCirculating Pump Minimum Pump PerformanceWater Circulating Pump High Water Temperature Limit ControlFlue Gas Passageways Cleaning Procedures Appliance AreaCombustion and Ventilation Air Burner Removal and CleaningHeat Exchanger Cleaning ElectricalSet-Up Procedure Adjusting Differential Air PressureFan Cleaning Combustion Air Fan AdjustmentIgnition System Checkout Adjustment ProcedureServicing Hot Surface Igniter and Ignition Module Sequence of Operation Glossary Prepurge Wiring BOX Connections Wiring BOX Connections Ladder Diagram Control BOX Connections Commercial Pool Heaters Appendix a View Menu Item Menu Description Appendix B