Installation and Service Manual

Figure 14 – Sidewall Combustion Air Inlet

Figure 15 – Air Inlet Cap for Sidewall Termination

To prevent recirculation of flue products from an adjacent vent cap into the combustion air inlet, follow all applicable clearance requirements in the latest edition of the National Fuel Gas Code and/or CAN/CGA-B149 Installation Code and instructions in the Installation and Service Manual.

You must install the combustion air inlet cap at least one foot (0.30m) above ground level and above normal snow levels.

The point of termination for the combustion air inlet cap must be at least 3 feet (0.91m) below the point of flue gas termination (powered vent cap) if it is located within 10 feet (3.05m) of the flue outlet from the powered vent cap. Make sure to properly install the air inlet cap assembly on the air inlet pipe.

You must install the combustion air inlet cap and the powered vent cap on the same wall and in the same pressure zone. Do not install the combustion air inlet cap closer than 10 feet (3.05m) from an inside corner of an L-shaped structure.

Vertical Rooftop Air Inlet

Use the vertical air inlet terminations available from the pool heater manufacturer, recommended and/or supplied by the vent manufacturer, or use two 90° elbows as described on page 24.

Figure 16 – Roof Top Combustion Air Inlet

Clearances

You must locate the air inlet termination elbow at least 12" (30cm) above the roof or above normal snow levels.

If the air inlet cap is within a 10 foot (3.05m) radius of the flue outlet, the point of termination for the combustion air inlet cap must be at least 3 feet (0.91m) below the point of flue gas termination (vent cap).

Do not install the combustion air inlet cap closer than 10 feet (3.05m) from an inside corner of an L-shaped structure.

Combined Air Inlet Points

The air inlet pipes from multiple pool heaters can be combined to a single common connection if the common air inlet pipe has a cross sectional area equal to or larger than the total area of all air inlet pipes connected to the common air inlet pipe.

Example: Two 10" air inlet pipes (78.5 in2 area each) have a total area of 157 in2 and will require a 15" (176.7 in2 area) common air inlet pipe.

The air inlet point for multiple pool heater air inlets must be provided with an exterior opening which has a free area equal to or greater than the total area of all air inlet pipes connected

13

Image 13
Contents GAS Heaters for Commercial Pool Applications Commercial Pool Heaters Unpacking General Product InformationCommercial Pool Heaters Product Identification Base for Combustible Floors Clearances from Combustible ConstructionCombustion Air Filter Freeze ProtectionCombustion Air Options InstallationCombustion Air from Interior Space Exhaust FansVenting Support General InformationVertical Vent Termination Clearances and Location Table B Sidewall Vent Termination Clearances and LocationLength of Air Inlet Pipe Combustion Air Inlet PipingSidewall Air Inlet Combined Air Inlet Points Vertical Rooftop Air InletConventional Negative Draft Venting Vent System OptionsNegative Draft Flue Outlet Piping Masonry Chimney InstallationsCommon Venting Systems Inspection of a Masonry Chimney Vertical DirectAire VentingSidewall Venting Vent KitsVenting of Flue Products Sidewall Venting Termination Sidewall FanSidewall Venting Without Fan Masonry Chimney Installation TABLE-E Horizontal DirectAire VentingDirect Venting Flue Pipe Materials Horizontal DV Venting TerminationCombustion Air Inlet Piping Air Inlet Piping Materials Length of Air Inlet PipeSealing Type-B Doublewall Vent Pipe or Galvanized Vent Pipe Vertical Rooftop Air Inlet Combined Combustion Air Inlet PointsOutdoor Vent/Air Inlet Location Outdoor Installation Venting3-Way Valve Cover Installation Combustion Air Fan Adjustment for startupGas Pressure Test Outdoor Vent Cap KitGas Piping Connecting Gas Piping to the Pool HeaterGas Train and Controls Venting of Combination Gas Valves Combination Gas ValvesChecking Gas Supply Pressure TABLE-JTable K Multiple Unit Installations Gas Supply Pipe SizingMeasuring Net Manifold Gas Pressure Gas Manifold Pressure AdjustmentPumped Automatic Bypass Auxiliary Mixed Water Limit ControlWay Valve Cover Heater is Within 15 Feet of Pool Piping Heaters are within 15 feet Perpendicular of Pool Piping Relief Valve Water Flow SwitchAutomatic Chlorinator and Chemical Feeders Service Indicator Option Pump Purge Delay OptionWay Automatic Bypass Valve Wiring TABLE-M Terminal Strip Connection OptionsLighting Instructions OperationTo Turn Off Gas To Pool Heater Pre-Start ChecklistStarting the Filter System Operation Error Messages Displayed by the Temperature Controller Programming ModeHot Surface Igniter and Ignition Control Module Diagnostic Status IndicationHot Surface Ignition Control Module Ignition Module Lockout FunctionsTABLE-N Access to Internal Control PanelIgnition and Control Timings TABLE-O Water ChemistryTest Recommended Level TABLE-PCirculating Pump Pipe Size RequirementsMinimum Pump Performance Heat ExchangerFlue Gas Passageways Cleaning Procedures High Water Temperature Limit ControlAppliance Area Water Circulating PumpHeat Exchanger Cleaning Burner Removal and CleaningElectrical Combustion and Ventilation AirFan Cleaning Adjusting Differential Air PressureCombustion Air Fan Adjustment Set-Up ProcedureServicing Hot Surface Igniter and Ignition Module Adjustment ProcedureIgnition System Checkout Sequence of Operation Glossary Prepurge Wiring BOX Connections Wiring BOX Connections Ladder Diagram Control BOX Connections Commercial Pool Heaters Appendix a View Menu Item Menu Description Appendix B