Goodman Mfg MH95/ACSH96/AMEH96/ GCH95/GME95/GCH9 Alternate Horizontal Vent Termination Dual Pipe

Page 20

90°

ELBOWS

3” - 24”

AIR

INTAKE

SCREEN

(OPTIONAL)

12" MIN. ABOVE HIGHEST ANTICIPATED

SNOW LEVEL

 

3” - 24”

 

12” MIN SEPARATION

 

3” MIN

OPTIONAL

 

INTAKE

 

SCREENS

12” MIN TO GRADE OR HIGHEST

 

ANTICIPATED SNOW LEVEL

Alternate Horizontal Vent Termination (Dual Pipe)

90°

ELBOWS

Termination of Multiple Direct Vent Furnaces

CONCENTRIC VENT TERMINATION

Refer to the directions provided with the Concentric Vent Kit (DCVK) for installation specifications.

SIDE WALL VENT KIT

AIR

INTAKE

3”-24” BETWEEN PIPES

This kit is to be used with 2” or 3” direct vent systems. The vent kit must terminate outside the structure and may be installed with the intake and exhaust pipes located side-by-side or with one pipe above the other. This kit is NOT intended for use with single pipe (indirect vent) installations.

Refer to the directions furnished with the Side Wall Vent Kit (p/n 0170K00000S) for installation specifications.

SCREEN

(OPTIONAL)

12" MIN. ABOVE

HIGHEST ANTICIPATED

SNOW LEVEL

Combustion Air Intake may also be snorkeled to obtain 12” min. ground clearance.

Alternate Vent Termination Above Anticipated Snow Level

(Dual Pipe)

In a basement installation, the pipes may be run between the joist spaces. If the pipes must go below the joist and then up into the last joist space to penetrate the header, two 45° elbows should be used to reach the header rather than two 90° elbows.

VENT/INTAKE TERMINATIONS FOR INSTALLATION OF MULTIPLE DIRECT VENT FURNACES

If more than one direct vent furnace is to be installed vertically through a common roof top, maintain the same minimum clear- ances between the exhaust vent and air intake terminations of adjacent units as with the exhaust vent and air intake terminations of a single unit.

If more than one direct vent furnace is to be installed horizontally through a common side wall, maintain the clearances as in the following figure. Always terminate all exhaust vent outlets at the same elevation and always terminate all air intakes at the same elevation.

20

X. CONDENSATE DRAIN LINES & DRAIN TRAP

A condensing gas furnace achieves its high level of efficiency by extracting almost all of the heat from the products of combustion and cooling them to the point where condensation takes place. The condensate which is generated must be piped to an appropri- ate drain location.

In upright installations, the furnace’s drain hoses may exit either the right or left side of the furnace. NOTE: If the alternate vent/flue outlet is utilized in an upright installation, the drain trap and drain connections must be located on the same side as the alternate vent/flue outlet.

In horizontal installations, the drain hoses will exit through the bottom (down side) of the unit with the drain trap suspended be- neath the furnace. The field-supplied drain system must be in accordance with all local codes and the instructions in the follow- ing sections.

Follow the bullets listed below when installing the drain system. Refer to the following sections for specific details concerning fur- nace drain trap installation and drain hose hook ups.

The drain trap supplied with the furnace must be used.

The drain line between furnace and drain location must maintain a 1/4 inch per foot downward slope toward the drain.

Do not trap the drain line in any other location than at the drain trap supplied with the furnace.

If the drain line is routed through an area which may see temperatures near or below freezing, precautions must be taken to prevent condensate from freezing within the drain line.

Image 20
Contents GCH95/GME95/GCH9 Table of Contents XIV. Startup Procedure & Adjustment XVII. Safety Circuit DescriptionXVIII. Troubleshooting XIX. MaintenanceCarbon Monoxide Poisoning Hazard Upflow/Horizontal Component IdentificationII. Safety Considerations What to do if YOU Smell GASElectrostatic Discharge ESD Precautions III. Product ApplicationIV. Location Requirements & Considerations GeneralClearances and Accessibility Suspended FurnaceFurnace Suspension Existing Furnace RemovalThermostat Location Thermostat InfluencesCombustion & Ventilation AIR Requirements See 5.3.3-a Horizontal Furnace VI. Installation PositionsVII. Horizontal Applications & Considerations Recommended Installation Positions VIII. Propane GAS /HIGH Altitude InstallationsAlternate Electrical and GAS Line Connections Drain PANDirect Vent Terminal Clearances IX. VENT/FLUE Pipe & Combustion AIR Pipe Dual Certification NON-DIRECT/DIRECT VentMaterials and Joining Methods Proper VENT/FLUE and Combustion AIR Piping PracticesIncreased Clearance Configuration Termination LocationsCanadian Venting Requirements Standard Furnace ConnectionsVent/Flue Pipe Cuts Alternate Furnace ConnectionsAlternate Vent/Flue Location NON-DIRECT Vent Single Pipe PipingDirect Vent Dual Pipe Piping Alternate Horizontal Vent Termination Dual Pipe Termination of Multiple Direct Vent FurnacesCondensate Drain Lines & Drain Trap Concentric Vent TerminationHose and Tube Identification Standard Right or Left Side Drain Hose ConnectionsDrain Trap Alternate VENT/FLUE Drain Hose ConnectionsUpright INSTALLATIONS-TRAP on Left Side Upright Standard Connections Left SideHorizontal Installations Right Side Down Upright Drain Trap Mounting Left or Right Side PanelLeft Side Down Horizontal Drain Trap Mounting Left or Right Side PanelWiring Harness XI. Electrical ConnectionsJunction Box Relocation Junction BOX RelocationThermostat Diagram Field Wiring for GME95 /AMEH96 Furnacewith 2-StageVolt Thermostat Wiring GME95/AMEH96 Furnace with 2-STAGE Condenser Field WiringGAS Piping Connections Nals XII. GAS Supply and PipingVolt Humidifier Rack, manifold or gas valve Horizontal Upflow Model Gas Piping ConnectionsPropane Gas Installation Typ Propane Gas Piping ChartXIII. Circulating AIR & Filters Propane GAS Tanks and PipingChecking Static Pressure 80% Furnace Shown, 90% Similar Duct Flange Cut OutsChecking Duct Static Bottom Return AIR Opening Upflow ModelsXIV. Startup Procedure & Adjustment Permanent Minimum Filter Area sq.Disposable Minimum Filter area sq. Filter LocationsWhite-Rodgers Model 36G54 Connected to Manometer White-Rodgers Model 36G54 Two-StageHoneywell Model VR9205 Connected to Manometer GAS Supply Pressure MeasurementGAS Input Rate Measurement Natural GAS only GAS Manifold Pressure Measurement and AdjustmentMeasuring Inlet Gas Pressure Alt. Method Circulator Blower Speeds Temperature Rise MeasurementTemperature Rise Circulator Blower FAN Timing Adjustment Setting Furnace Operating ModePower UP Heating ModePage XVIII. Troubleshooting XIX. Maintenance XX. Before Leaving AN Installation XXI. Repair & Replacement PartsTroubleshooting Chart No signalContinuously MH95 Blower Performance DataACSH96 AMEH96 GCH95 / GCH9115 GME95 Wiring Diagram MH950453,0704,0905D MH950703,0904,1155MH950905CX GME95 / AMEH96 GAS Vent Directly BELOW. Keep Clear of ALL Obstructions ExemptionsThis page Left Intentionally Blank This page Left Intentionally Blank This page Left Intentionally Blank Quality Makes the Difference