Trane RT-SVX10C-EN No Step Surface, Unit Inspection As soon as the unit arrives at the job site

Page 15

Unit Inspection

As soon as the unit arrives at the job site

[ ] Verify that the nameplate data matches the data on the sales order and bill of lading (including electrical data).

[ ] Verify that the power supply complies with the unit name- plate specifications.

[ ] Verify that the power supply complies with the electric heater specifications on the uit nameplate.

[ ] Visually inspect the exterior of the unit, including the roof, for signs of shipping damage.

[ ] Check for material shortages. Refer to the Component Layout and Shipwith Location illustration.

If the job site inspection of the unit reveals damage or mate- rial shortages, file a claim with the carrier immediately. Specify the type and extent of the damage on the "bill of lading" before signing.

[ ] Visually inspect the internal components for shipping damage as soon as possible after delivery and before it is stored. Do not walk on the sheet metal base pans.

WARNING

No Step Surface!

FOR ACCESS TO COMPONENTS, THE BASE SHEET METAL SURFACE MUST BE REINFORCED.

Bridging between the unit's main supports may consist of multiple 2 by 12 boards or sheet metal grating.

Failure to comply could result in death or severe personal injury from falling.

[ ] If concealed damage is discovered, notify the carrier's terminal of damage immediately by phone and by mail. Concealed damage must be reported within 15 days.

Request an immediate joint inspection of the damage by the carrier and the consignee. Do not remove damaged material from the receiving location. Take photos of the damage, if possible. The owner must provide reasonable evidence that the damage did not occur after delivery.

[ ] Remove the protective plastic coverings that shipped over the compressors.

Installation

Storage

Take precautions to prevent condensate from forming inside the unit’s electrical compartments and motors if:

a. the unit is stored before it is installed; or,

b. the unit is set on the roof curb, and temporary heat is provided in the building. Isolate all side panel service entrances and base pan openings (e.g., conduit holes, S/A and R/A openings, and flue openings) from the ambient air until the unit is ready for startup.

Note: Do not use the unit's heater for temporary heat without first completing the startup procedure detailed under "Starting the Unit".

Trane will not assume any responsibility for

equipment damage resulting from condensate accumulation on the unit's electrical and/or mechanical components.

Unit Clearances

Figure 3-1 illustrates the minimum operating and service clearances for either a single or multiple unit installation. These clearances are the minimum distances necessary to assure adequate serviceability, cataloged unit capacity, and peak operating efficiency.

Providing less than the recommended clearances may re- sult in condenser coil starvation, "short-circuiting" of ex- haust and economizer airflows, or recirculation of hot con- denser air.

Unit Dimensions & Weight Information

Overall unit dimensional data for a SAHF (20 thru 75 Ton) cooling only unit is illustrated in Figure 3-2A. Tables 3-1A, 3-1B, and 3-1C list the dimensions. Dimensional data for SEH_, SFH_, SLH_, SSH_, and SXH_ (20 thru 130 Ton) units are illustrated in Figure 3-2B. Tables 3-2A, 3-2B, and 3-2C list the dimensions for the 20 thru 75 Ton units. Di- mensions for 90 through 130 Ton units are listed on the il- lustration in Figure 3-2C.

ACenter-of-Gravity illustration and the dimensional data is shown in Figure 3-3.

Table 3-3 list the typical unit and curb operating weights. Weights shown represent approximate operating weights. Actual weights are stamped on the unit nameplate.

14

Image 15
Contents Models Later Design SequenceWith 3-DTMScroll Compressors Overview of Manual Literature Change HistoryTable of Contents Model Number Description General InformationDigit 3 Unit Airflow Unit Description Fiberglass WoolHazard Identification General Information Commonly Used AcronymsSupply AIR General InformationCFM Ventilation Control Module VCM Design special option onlyLead-Lag Constant Volume CV Units Unit Component Layout and Shipwith Locations Variable Air Volume VAV UnitsGeneral Information Space Temperature Averaging Control Module Locations for SHF 40, 60, 70 & 75 Ton Units Table of Contents Storage Unit Dimensions & Weight InformationNo Step Surface Unit Inspection As soon as the unit arrives at the job sitePage Sahf Cooling-Only Units 20 thru 75 Ton Electrical Entrance Data Unit Dimensions InstallationUnit Dimensional Data Dimensions Size Unit Base Dimensional Data DimensionsSEHF, SFHF, SLHF, SSHF, Sxhf Units 20 thru 75 Ton Unit Size Furnace Dimensions Note Size/MBH Length Height Unit Base Dimensional Data Dimensions SizeUnit Dimensions Size Electrical Entrance Data Unit Dimensions SizeSHG Cooling & Heating Units 90 through 130 Ton Sshf SahfSehf SlhfRoof Curb and Ductwork SE,SLSahf Sshf Sfhf Sxhf Sehg Sfhg Sxhg HF/G Pitch Pocket Location Installation Unit Rigging & PlacementIf a Trane Curb Accessory Kit is not used Heavy ObjectsTypical Unit Rigging Unit Base & Roof Curb Section Requirements for Electric Heat Units Main Electrical Power RequirementsInstallation Field Installed Control Wiring General Unit RequirementsInstallation Condensate Drain Connections Page Removing Supply and Exhaust Fan Shipping Channels Motors 5Hp Page Units with StatitracTM Installation Sensor & Tubing InstallationConnecting the Gas Supply Line to the Furnace Gas Train Hazardous Gases and Flammable VaporsGas Heat Units SFH 350 MBH 850 MBH Hot Water Heat Units SLH Flue Assembly InstallationFlue Assembly 1000 MBH Modulating 500 MBH 1000 MBHSSHG-90 Steam Heat Units SSHThrough 130 Ton units Page Hazardous Voltage Live Electrical ComponentsUse Copper Conductors Only Typical Field Power Wiring 20 thru 75 Ton Page FLA Supply Fan Motor FLA ea HorsepowerCondenser Fans Total FLA Exhaust Fan MotorCombustion Blower Motor Sfhf OnlyUnit Tonnage No. of Compressors Tonnage Type Designation On the Next Single Source Power 380V, 415V, 460V,Load Definitions Load = Current of the Largest Motor Compressor or FAN MotorMCA = 1.25 x Load MOP = 1.25 x Load Power Wire Sizing and Protection Device EquationsDisconnect Switch Sizing DSS Dual Source Power units 200VControls using 24 VAC Installation Controls using DC Analog Input/OutputsConstant Volume System Controls Constant Volume or Variable Air Volume System Controls Variable Air Volume System ControlsDepressurize PressurizeFire Purge16A Refer to Wiring Notes on16B Page 17A 17B Input Voltage VAV SetpointTable of Contents Sequence of Operation Cooling Sequence of OperationPropane Gas Gas Heating Sequence of OperationFenwal Ignition System Unit Start-UpModulating Gas Sequence of Operation Flame FailureFull and Limited Modulating Gas Furnace Electric Heat Sequence of Operation Unit Start-Up Wet Heat Sequence of OperationFreeze Protection Unit Power Compressor DamageElectrical Phasing Voltage Supply and Voltage Imbalance Voltage SupplyVoltage Imbalance IGV Service Test Guide for Component OperationSupply FAN If all of the fans are rotating backwards System Airflow Measurements Constant Volume SystemsRotating Components Verifying Proper Fan RotationCondenser Fan Location with Human Interface Designator Variable Air Volume Systems Optional with all units equipped with an economizer Exhaust Airflow MeasurementTraqTM Sensor Airflow Measurement Optional with all UnitsTon Supply Fan Performance without Inlet Guide Vanes 20 & 25 Ton Supply Fan Performance without Inlet Guide VanesWocfm 1200 RPM 40 HP 40% 300 RP Standard Evaporator Coil 20000 30000 40000 50000 60000 Drop Ton Supply Fan Performance with Inlet Guide Vanes 20 & 25 Ton Supply Fan Performance with Inlet Guide Vanes15 HP 900 RPM 80% 10 HP RPM AIR Through 75 Ton Component Static Pressure Drops Inches W.CSTD AIRCFM RPM BHP HF-C30 000 HF-C20 000HF-C25 000 10,000AIR RPM BHP RPM BHP BHP RPM BHP RPM BHPFresh Air & Return Air Damper Operation Economizer Damper AdjustmentTo Adjust the Fresh Air Damper Travel Exhaust Air DampersTon Units Damper Travel Adjustment PositionConnecting Rod Crank Arm Hole Configuration70 & 105 Ton Fresh Air & Return Air Linkage AdjustmentCompressor Start-Up All SystemsAt Low Ambient Start-Up Compressor Operational SoundsRefrigerant Charging At ShutdownCompressor Locations Cooling Cycle Pressure Curve 340 320 Full Load 380 360 340 OD Ambient Full Load 380 360 340 OD Ambient 320 240 220 380 360 OD Ambient Thermostatic Expansion Valves Charging by SubcoolingLow Ambient Dampers Gas Furnace Start-Up Electric, Steam and Hot Water Start-UpTwo Stage Gas Furnace High-Fire AdjustmentCombustion Air Adjustment O2 Low-Fire Adjustment 500 MBH, 850 & 1,000 MBH onlyMBH Firing ManifoldCO2 Pressure Full Modulating Gas Furnace Heat ExchangerUnit control Limited Modulating Gas Furnace Unit Start-Up Modulating Gas RegulatorModulating Gas Regulator Legend Typical Gas Furnace Unit Start-Up Final Unit CheckoutService & Maintenance Unit Internal Fuse Replacement Data & VFD Factory Settings Service & MaintenanceModel Type Unit Model Box-type Note QtyQty Size of each Wet Heat Coil Fin Data Total Coil FinsService & Maintenance Fan Belt Adjustment Scroll Compressor Replacement Suction Line Filter/Drier InstallationGripbelts Gripnotch Cross Small P.D Section Range Min Max Hazardous Voltage! w/Capacitors VFD Programming ParametersSupply and Exhaust Fan VFD Programming Parameters Service & Maintenance Monthly Maintenance FiltersCooling Season Heating Season Coil CleaningCoil Cleaners Contains RefrigerantSteam or Hot Water Coils Final Process Index See Figure Gate type valve 36-37 See -12 Figure See VOM Contacts -16 Figure Equipment Damage From Ultraviolet UV Lights Warranty and Liability Clause115 116