Trane RT-SVX10C-EN specifications General Unit Requirements, Main Electrical Power Requirements

Page 26

General Unit Requirements

The checklist listed below is a summary of the steps re- quired to successfully install a Commercial rooftop unit. This checklist is intended to acquaint the installing person- nel with what is required in the installation process. It does not replace the detailed instructions called out in the appli- cable sections of this manual.

[ ] Check the unit for shipping damage and material short- age; file a freight claim and notify Trane office.

[ ] Verify that the installation location of the unit will provide the required clearance for proper operation.

[ ] Assemble and install the roof curb. Refer to the current edition of SAHF-IN-5 for 20 through 75 Ton units or SXHG-IN-2 for 90 through 130 Ton units.

[ ] Fabricate and install ductwork; secure ductwork to curb.

[ ] Install pitch pocket for power supply through building roof. (If applicable)

[ ] Rigging the unit.

[ ] Set the unit onto the curb; check for levelness.

[ ] Ensure unit-to-curb seal is tight and without buckles or cracks.

[ ] Install and connect condensate drain lines to each evaporator drain connection.

[ ] Remove the shipping hardware from each compressor assembly.

[ ] Remove the shipping hold-down bolts and shipping chan- nels from the supply and exhaust fans ordered with rub- ber or spring isolators.

[ ] Check all optional supply and exhaust fan spring isola- tors for proper adjustment.

[ ] Verify that all plastic coverings are removed from the compressors.

[ ] Verify all discharge and liquid line service valves (one per circuit) are back seated.

Main Electrical Power Requirements

[ ] Verify that the power supply complies with the unit name- plate specifications.

[ ] Inspect all control panel components; tighten any loose connections.

[ ] Connect properly sized and protected power supply wir- ing to a field-supplied/installed disconnect and unit

[ ] Properly ground the unit.

Note: All field-installed wiring must comply with NEC and applicable local codes.

Installation (Continued)

Field Installed Control Wiring

[ ] Complete the field wiring connections for the constant volume controls as applicable. Refer to "Field Installed Control Wiring" for guidelines.

[ ] Complete the field wiring connections for the variable air volume controls as applicable. Refer to "Field Installed Control Wiring" for guidelines.

Note: All field-installed wiring must comply with NEC and applicable local codes.

Requirements for Electric Heat Units

All SEHF Units (380 minimum voltage) & SEHG units.

[ ] Verify that the power supply complies with the electric heater specifications on the unit and heater nameplate.

[ ] Inspect the heater junction box and control panel; tighten any loose connections.

[ ] Check electric heat circuits for continuity.

SEHF Units w/200V or 230V Electric Heat: (Requires Separate Power Supply to Heater)

[ ] Connect properly sized and protected power supply wir- ing for the electric heat from a dedicated, field- supplied/ installed disconnect to terminal block 4TB2, or to an op- tional unit mounted disconnect switch 4S15.

Requirements for Gas Heat

[ ] Gas supply line properly sized and connected to the unit gas train.

[ ] All gas piping joints properly sealed.

[ ] Drip leg Installed in the gas piping near the unit.

[ ] Gas piping leak checked with a soap solution. If piping connections to the unit are complete, do not pressurize piping in excess of 0.50 psig or 14 inches w.c. to prevent component failure.

[ ] Main supply gas pressure adequate.

[ ] Flue Tubes clear of any obstructions.

[ ] Factory-supplied flue assembly installed on the unit.

[ ] Connect the 3/4" CPVC furnace drain stubout to a proper condensate drain.

Requirements for Hot Water Heat (SLH_)

[ ] Route properly sized water piping through the base of the unit into the heating section.

[ ] Install the factory-supplied, 3-way modulating valve.

[ ] Complete the valve actuator wiring.

25

Image 26
Contents With 3-DTMScroll Compressors ModelsLater Design Sequence Literature Change History Overview of ManualTable of Contents General Information Model Number DescriptionDigit 3 Unit Airflow General Information Commonly Used Acronyms Fiberglass WoolHazard Identification Unit DescriptionGeneral Information Supply AIRVentilation Control Module VCM Design special option only CFMLead-Lag Constant Volume CV Units Variable Air Volume VAV Units Unit Component Layout and Shipwith LocationsGeneral Information Space Temperature Averaging Control Module Locations for SHF 40, 60, 70 & 75 Ton Units Table of Contents Unit Inspection As soon as the unit arrives at the job site Unit Dimensions & Weight InformationNo Step Surface StoragePage Sahf Cooling-Only Units 20 thru 75 Ton Unit Base Dimensional Data Dimensions InstallationUnit Dimensional Data Dimensions Size Electrical Entrance Data Unit DimensionsSEHF, SFHF, SLHF, SSHF, Sxhf Units 20 thru 75 Ton Electrical Entrance Data Unit Dimensions Size Unit Base Dimensional Data Dimensions SizeUnit Dimensions Size Unit Size Furnace Dimensions Note Size/MBH Length HeightSHG Cooling & Heating Units 90 through 130 Ton Slhf SahfSehf SshfSahf Sshf Sfhf Sxhf Sehg Sfhg Sxhg HF/G Roof Curb and DuctworkSE,SL Heavy Objects Installation Unit Rigging & PlacementIf a Trane Curb Accessory Kit is not used Pitch Pocket LocationTypical Unit Rigging Unit Base & Roof Curb Section General Unit Requirements Main Electrical Power RequirementsInstallation Field Installed Control Wiring Requirements for Electric Heat UnitsInstallation Condensate Drain Connections Page Removing Supply and Exhaust Fan Shipping Channels Motors 5Hp Page Installation Sensor & Tubing Installation Units with StatitracTMGas Heat Units SFH Connecting the Gas Supply Line to the Furnace Gas TrainHazardous Gases and Flammable Vapors 350 MBH 850 MBH 1000 MBH Modulating 500 MBH 1000 MBH Flue Assembly InstallationFlue Assembly Hot Water Heat Units SLHSteam Heat Units SSH SSHG-90Through 130 Ton units Page Use Copper Conductors Only Hazardous VoltageLive Electrical Components Typical Field Power Wiring 20 thru 75 Ton Page Exhaust Fan Motor Supply Fan Motor FLA ea HorsepowerCondenser Fans Total FLA FLAUnit Tonnage No. of Compressors Tonnage Type Designation CombustionBlower Motor Sfhf Only = Current of the Largest Motor Compressor or FAN Motor Single Source Power 380V, 415V, 460V,Load Definitions Load On the NextDual Source Power units 200V Power Wire Sizing and Protection Device EquationsDisconnect Switch Sizing DSS MCA = 1.25 x Load MOP = 1.25 x LoadConstant Volume System Controls Controls using 24 VACInstallation Controls using DC Analog Input/Outputs Variable Air Volume System Controls Constant Volume or Variable Air Volume System ControlsPressurize DepressurizePurge FireRefer to Wiring Notes on 16A16B Page 17A 17B VAV Setpoint Input VoltageTable of Contents Cooling Sequence of Operation Sequence of OperationUnit Start-Up Gas Heating Sequence of OperationFenwal Ignition System Propane GasFull and Limited Modulating Gas Furnace Modulating Gas Sequence of OperationFlame Failure Freeze Protection Electric Heat Sequence of OperationUnit Start-Up Wet Heat Sequence of Operation Electrical Phasing Unit PowerCompressor Damage Voltage Imbalance Voltage Supply and Voltage ImbalanceVoltage Supply Service Test Guide for Component Operation IGVSupply FAN Verifying Proper Fan Rotation System Airflow Measurements Constant Volume SystemsRotating Components If all of the fans are rotating backwardsCondenser Fan Location with Human Interface Designator Variable Air Volume Systems Optional with all Units Exhaust Airflow MeasurementTraqTM Sensor Airflow Measurement Optional with all units equipped with an economizer20 & 25 Ton Supply Fan Performance without Inlet Guide Vanes Ton Supply Fan Performance without Inlet Guide VanesWocfm 1200 RPM 40 HP 40% 300 RP Standard Evaporator Coil 20000 30000 40000 50000 60000 Drop 20 & 25 Ton Supply Fan Performance with Inlet Guide Vanes Ton Supply Fan Performance with Inlet Guide Vanes15 HP 900 RPM 80% 10 HP RPM Through 75 Ton Component Static Pressure Drops Inches W.C AIRCFM RPM BHP STDAIR 10,000 HF-C20 000HF-C25 000 HF-C30 000RPM BHP BHP RPM BHP RPM BHP AIR RPM BHPExhaust Air Dampers Economizer Damper AdjustmentTo Adjust the Fresh Air Damper Travel Fresh Air & Return Air Damper OperationConfiguration Damper Travel Adjustment PositionConnecting Rod Crank Arm Hole Ton UnitsAll Systems Fresh Air & Return Air Linkage AdjustmentCompressor Start-Up 70 & 105 TonAt Shutdown Compressor Operational SoundsRefrigerant Charging At Low Ambient Start-UpCompressor Locations Cooling Cycle Pressure Curve 340 320 Full Load 380 360 340 OD Ambient Full Load 380 360 340 OD Ambient 320 240 220 380 360 OD Ambient Low Ambient Dampers Thermostatic Expansion ValvesCharging by Subcooling Electric, Steam and Hot Water Start-Up Gas Furnace Start-UpLow-Fire Adjustment 500 MBH, 850 & 1,000 MBH only High-Fire AdjustmentCombustion Air Adjustment O2 Two Stage Gas FurnaceCO2 Pressure MBHFiring Manifold Unit control Full Modulating Gas FurnaceHeat Exchanger Modulating Gas Regulator Legend Limited Modulating Gas Furnace Unit Start-UpModulating Gas Regulator Unit Start-Up Final Unit Checkout Typical Gas FurnaceService & Maintenance Service & Maintenance Unit Internal Fuse Replacement Data & VFD Factory SettingsWet Heat Coil Fin Data Total Coil Fins Unit Model Box-type Note QtyQty Size of each Model TypeService & Maintenance Fan Belt Adjustment Gripbelts Gripnotch Cross Small P.D Section Range Min Max Scroll Compressor ReplacementSuction Line Filter/Drier Installation Supply and Exhaust Fan VFD Programming Parameters Hazardous Voltage! w/CapacitorsVFD Programming Parameters Cooling Season Service & Maintenance Monthly MaintenanceFilters Coil Cleaning Heating SeasonSteam or Hot Water Coils Coil CleanersContains Refrigerant Final Process Index See Figure Gate type valve 36-37 See -12 Figure See VOM Contacts -16 Figure Warranty and Liability Clause Equipment Damage From Ultraviolet UV Lights115 116