5.Next, remove the four (4) screws holding the heater to the stand. Position heater out of the way of the installation area.

5.Next, remove the four (4) screws holding the heater to the stand. Position heater out of the way of the installation area.

6.Check that the pedestal stand is still aligned with the marks and now, mark the outside air opening of the stand on the pad.

7.Next, mark the center line of the outside air opening. Set stand aside for now.

8.Next, cut a 4 1/4" diameter hole in the pad and continue through the floor.

9.Now, reposition the pedestal stand and set on the pad being sure to line the stand up with the reference marks.

10.Using an electric drill and 3/8" masonry bit, drill four (4) holes in the protective pad using the holes in the bottom side lips of the pedestal stand as a guide. Be careful to drill only through the pad and not into the floor. Change the bit to a 1/4" metal bit and drill through the floor.

11.Using four (4) 3/8" x 1-1/2" lag bolts, secure the pedestal stand and pad to the floor of the mobile home.

12.Set the heater back onto the stand and resecure using the screws.

13.Obtain the outside air duct from the box in the pedestal kit marked FA P21B.

14.From under the mobile home, slip the duct up through the 4-1/4" hole. Push up until the face of the outside air duct contacts the underside of the floor of the mobile home. For certain floor thickness, you may have to shorten the length of the outside air duct.

15.Secure the outside air duct to the floor using the four (4) #10 x 1" screws provided. See Figure 12.

26

Image 28
Contents Page Page TABLE OF CONTENTS Page INSTALLATION, OPERATION, AND MAINTENANCE INSTRUCTIONS MODELREAD THIS FIRST IMPORTANT INSTRUCTIONSSECTION INTRODUCTIONSECTION MASONRY INSERT INSTALLATION MODELMINIMUM CLEARANCES K* FACTORS OF ALTERNATE MATERIALSMaterial Required ThicknessPOSSIBLE TOOLS NEEDED FOR INSTALLATION INSTALLATION PREPARATION FIREPLACEInstallation Procedure Positioning the Heater Mounting the Trim PanelsFinal Check Final Check 5.Check for smoke leaks around the doors SECTION PRE-FABINSERT INSTALLATION PREPARING THE STOVE FOR INSTALLATION SECTION RESIDENTIAL FREE-STANDINGINSTALLATIONMINIMUM CLEARANCE TO COMBUSTIBLE MATERIAL ALTERNATE FLOOR PROTECTORS MATERIAL K* FACTORS OF ALTERNATE MATERIALSMaterial Required ThicknessChimney DETERMINING THE CHIMNEY LOCATIONB.Wall Exit Into Metal Tee-Box C. Wall Exit Into Masonry Using Single Wall Pipe D. Ceiling Exit-CloseClearance ALCOVE INSTALLATION CLEARANCES FINAL CHECK CLEARANCES FOR MODEL MINIMUM CLEARANCES TO COMBUSTIBLES FREE-STANDINGCLEARANCES FOR MODEL MODEL 85 INSTALLATION OF CLOSE CLEARANCE SHIELDS OptionalFREE-STANDINGMOBILE HOME INSTALLATION FOR MINIMUM CLEARANCES SEE PAGE FLOOR PROTECTIONCHIMNEY SECTIONTOOLS FOR INSTALLATION PREPARING THE HEATER FOR INSTALLATIONWARNING DO NOT INSTALL IN A SLEEPING ROOM PREPARING THE ROOM HEATER LOCATION5.Next, remove the four 4 screws holding the heater to the stand. Position heater out of the way of the installation area Ceiling Exit Using Close Clearance Listed Chimney FINAL CHECK SECTION WOOD HEATER SAFETY SECTION OPERATION BUILDING A FIRE ROOM AIR BLOWER OPERATION TROUBLESHOOTING PROBLEMSOLUTION POSSIBLE CAUSEEPA COMPLIANCE STATUS MODEL WOOD STOVEREPLACEMENT PARTS FOR THE MODEL WARRANTY TIME PERIODS PROCEDUREPRODUCTS COVERED PRODUCTS NOT COVEREDCONDITIONS AND EXCLUSIONS OTHER RIGHTS