New Buck Corporation 85 installation instructions B.Wall Exit Into Metal Tee-Box

Page 18
B.Wall Exit Into Metal Tee-Box

three (3) sheet metal screws or rivets. Next, install an optional New Buck Corporation chimney connector to the flue exit of the heater or you may use “Ell” brackets to fasten the pipe to the stove.

4.Install Single Wall Connector and chimney system per manufacturer’s written operating in- structions. See manufacturer’s list of tested pipes in this manual.

Figure 5

Figure 6

B.Wall Exit Into Metal Tee-Box

1.Mark the plumb line on the wall directly behind the center of the heater. (See Figure 6.)

NOTE: When using #24 ga. minimum blue or black steel pipe maintain 18" between pipe and ceiling.

2.Place the vertical portion of the heater pipe and the elbow in position and project a point onto the plumb line level with the center of the elbow.

3.Measure up so there will be at least 1/4" rise per foot of horizontal connector pipe,

16

Image 18
Contents Page Page TABLE OF CONTENTS Page READ THIS FIRST INSTALLATION, OPERATION, ANDMAINTENANCE INSTRUCTIONS MODEL IMPORTANT INSTRUCTIONSSECTION INTRODUCTIONSECTION MASONRY INSERT INSTALLATION MODELMaterial MINIMUM CLEARANCESK* FACTORS OF ALTERNATE MATERIALS Required ThicknessPOSSIBLE TOOLS NEEDED FOR INSTALLATION INSTALLATION PREPARATION FIREPLACEInstallation Procedure Positioning the Heater Mounting the Trim PanelsFinal Check Final Check 5.Check for smoke leaks around the doors SECTION PRE-FABINSERT INSTALLATION SECTION RESIDENTIAL FREE-STANDINGINSTALLATION PREPARING THE STOVE FOR INSTALLATIONMINIMUM CLEARANCE TO COMBUSTIBLE MATERIAL Material ALTERNATE FLOOR PROTECTORS MATERIALK* FACTORS OF ALTERNATE MATERIALS Required ThicknessChimney DETERMINING THE CHIMNEY LOCATIONB.Wall Exit Into Metal Tee-Box C. Wall Exit Into Masonry Using Single Wall Pipe D. Ceiling Exit-CloseClearance ALCOVE INSTALLATION CLEARANCES FINAL CHECK CLEARANCES FOR MODEL MINIMUM CLEARANCES TO COMBUSTIBLES FREE-STANDINGCLEARANCES FOR MODEL MODEL 85 INSTALLATION OF CLOSE CLEARANCE SHIELDS OptionalCHIMNEY FREE-STANDINGMOBILE HOME INSTALLATIONFOR MINIMUM CLEARANCES SEE PAGE FLOOR PROTECTION SECTIONWARNING DO NOT INSTALL IN A SLEEPING ROOM TOOLS FOR INSTALLATIONPREPARING THE HEATER FOR INSTALLATION PREPARING THE ROOM HEATER LOCATION5.Next, remove the four 4 screws holding the heater to the stand. Position heater out of the way of the installation area Ceiling Exit Using Close Clearance Listed Chimney FINAL CHECK SECTION WOOD HEATER SAFETY SECTION OPERATION BUILDING A FIRE ROOM AIR BLOWER OPERATION SOLUTION TROUBLESHOOTINGPROBLEM POSSIBLE CAUSEEPA COMPLIANCE STATUS MODEL WOOD STOVEREPLACEMENT PARTS FOR THE MODEL PRODUCTS COVERED WARRANTY TIME PERIODSPROCEDURE PRODUCTS NOT COVEREDCONDITIONS AND EXCLUSIONS OTHER RIGHTS