1. Top Vent - Horizontal Termination - (continued)
Top Vent - Horizontal Termination
Venting with 2 elbows
| V Minimum | H1 + H2 MAXIMUM | |||
|
|
| |||
|
|
|
| ||
| 90° Elbow | 1 ft. |
| 305 mm | |
|
|
|
|
|
|
1 ft. |
| 305 mm | 2 ft. |
| 610 mm |
|
|
|
|
|
|
2 ft. |
| 610 mm | 4 ft. |
| 1.2 m |
|
|
|
|
|
|
3 ft. |
| 914 mm | 6 ft. |
| 1.8 m |
|
|
|
|
|
|
4 ft. |
| 1.2 m | 15 ft. |
| 4.6 m |
|
|
|
|
|
|
H1 + H2 MAX. =15 ft. (4.6 m)
V + H1 + H2 MAX. = 40 ft. (12.2 m)
Note: Use SLP Series components only.
Note: There MUST be a 25% reduction in total H when using flex vent except when using the simple up and out installation (see Figure 7.3).