F. Install Metal Roof Flashing

F. Install Metal Roof Flashing

See minimum vent heights for various pitched roofs (Figure 10.11) to determine the length of pipe to extend through the roof.

Slide the roof flashing over the pipe sections extending through the roof as shown in Figure 10.12.

 

 

HORIZONTAL

 

 

OVERHANG

2 FT.

20 INCHES MIN.

VERTICAL

MIN.

 

 

WALL

 

LOWEST

 

 

 

DISCHARGE

 

 

OPENING

 

GAS DIRECT VENT

 

 

TERMINATION CAP

 

 

 

 

X

 

 

12

 

 

ROOF PITCH

 

 

IS X/ 12

 

H (MIN.) - MINIMUM HEIGHT FROM ROOF

 

TO LOWEST DISCHARGE OPENING

Roof Pitch

 

H (Min.) Ft.

Flat to 6/12........................................1.0*

Over 6/12 to 7/12............................1.25*

Over 7/12 to 8/12..............................1.5*

Over 8/12 to 9/12..............................2.0*

Over 9/12 to 10/12............................. 2.5

Over 10/12 to 11/12 ......................... 3.25

Over 11/12 to 12/12 ........................... 4.0

Over 12/12 to 14/12........................... 5.0

Over 14/12 to 16/12........................... 6.0

Over 16/12 to 18/12........................... 7.0

Over 18/12 to 20/12........................... 7.5

Over 20/12 to 21/12........................... 8.0

* 3 foot minimum in snow regions

Figure 10.11 Minimum Height From Roof To Lowest Discharge

Opening

 

 

NOTICE: Failure to properly caulk the roof flashing and pipe seams may permit entry of water.

Caulk the gap between the roof flashing and the outside diameter of the pipe.

Caulk the perimeter of the flashing where it contacts the roof surface. See Figure 10.12.

Caulk the overlap seam of any exposed pipe sections that are located above the roof line.

CAULK

Figure 10.12

G. Assemble and Install Storm Collar

CAUTION! Risk of Cuts, Abrasions or Flying Debris. Wear protective gloves and safety glasses during instal-

lation. Sheet metal edges are sharp.

Connect both halves of the storm collar with two screws (see Figure 10.13).

Wrap the storm collar around the exposed pipe section closest to the roof and align brackets. Insert a bolt (provided) through the brackets and tighten the nut to complete the storm collar assembly. Make sure the collar is tight against the pipe section.

Slide the assembled storm collar down the pipe section until it rests on the roof flashing (see Figure 10.14).

Caulk around the top of the storm collar (see Figure 10.15).

Figure 10.13 Assembling the Storm Collar

Figure 10.14 Assembling the Storm Collar Around the Pipe

Heat & Glo • SLR-C2292-900 Rev. D • 8/12

43

Image 43
Contents Owner’s Manual NOTICEModel SLR-CCOSMO •What to do if you smell gasHomeowner Reference Information A. CongratulationsUser Guide Table of ContentsSafety Alert Key Installer Guide13 Finishing 14 Appliance Setup15 Troubleshooting  = Contains updated informationWARRANTY PERIOD B. Limited Lifetime WarrantyLIMITED LIFETIME WARRANTY WARRANTY COVERAGEThis warranty is void if B. Limited Lifetime Warranty continuedWARRANTY CONDITIONS WARRANTY EXCLUSIONSB. Tempered Glass Specifications D. High Altitude Installations1 Listing and Code Approvals A. Appliance CertificationInstallation of Carbon Monoxide Detectors WARNING! Choking Hazard! Keep glass rock media A. Gas Fireplace Safety2 Operating Instructions User Guide B. Your FireplaceG. Before Lighting Fireplace E. Fixed Glass AssemblyC. Clear Space D. Decorative Doors and FrontsLIGHTING INSTRUCTIONS IPI H. Lighting Instructions IPIFinal inspection by FOR YOUR SAFETY READ BEFORE LIGHTING•Some people may be sensitive to smoke and odors J. Frequently Asked QuestionsI. After Fireplace is Lit Initial Break-inProcedureRemote Control 3 Maintenance and ServiceA. Maintenance Tasks-Homeowner Glass CleaningControl Compartment and Firebox Top B.Maintenance Tasks-QualifiedService TechnicianGasket Seal and Glass Assembly Inspection FireboxWALL SWITCH Getting StartedA. Typical Appliance System Installer GuideC. Tools and Supplies Needed B. Design and Installation ConsiderationsD. Inspect Appliance and Components A. Selecting Appliance Location 5 Framing and ClearancesHeat & Glo • SLR-C• 2292-900Rev. D • 8/12 B. Constructing the Appliance ChaseMINIMUM FRAMING DIMENSIONS C. ClearancesD. Mantel and Wall Projections Heat & Glo • SLR-C• 2292-900Rev. D • 8/12 Figure 5.8 Non-CombustibleZone3-1/2IN A. Vent Termination Minimum Clearances 6 Termination LocationsCovered Alcove Applications = AREA WHERE TERMINAL IS NOT PERMITTEDV= VENT TERMINAL X = AIR SUPPLY INLET B. Vent Table Key 7 Vent Information and DiagramsE. Vent Diagrams A. Approved PipeVenting with 1 elbow Top Vent - Horizontal TerminationTop Vent - Horizontal Termination 1. Top Vent - Horizontal Termination - continuedVenting with 2 elbows INSTALLED HORIZONTALLYSLR-C Venting with 3 elbows1. Top Vent - Horizontal Termination - continued Top Vent - Horizontal Termination1. Top Vent - Horizontal Termination - continued INSTALLED HORIZONTALLYINSTALLED HORIZONTALLY H2 H1 V1PILOT HOLES Top Vent - Vertical Termination No ElbowsV1 = 44 ft. Max. 13.4 m Exhaust restrictor InstructionsV1 Minimum Top Vent - Vertical TerminationVenting with 2 elbows SLR-CV1 Minimum Top Vent - Vertical TerminationVenting with 3 elbows SLR-CV1 MIN Venting with 4 elbowsTop Vent - Vertical Termination V3 H2 H1 V1Clearances to Combustibles Coaxial to Colinear VentingPrior to installing the gas appliance Table•Vent this appliance directly outside TOP VENT•Use separate vent system for this appliance •Between ceiling firestops 8 Vent Clearances and FramingA. Pipe Clearances to Combustibles B. Wall Penetration FramingC. Install the Ceiling Firestop Flat Ceiling Installation D. Install Attic Insulation ShieldVaulted Ceiling Installation A. Top Vent 9 Appliance Preparation•Insulation backing or plastic B. Securing and Leveling the ApplianceWARNING! Risk of Fire! Prevent contact with •Sagging or loose insulationA. Assemble Vent Sections 10 Installing Vent Pipe SLP PipeC. Secure The Vent Sections B. Assemble Slip SectionsPilot hole D. Disassemble Vent Sections E. Install Decorative Ceiling ComponentsG. Assemble and Install Storm Collar F. Install Metal Roof FlashingCAULK Figure 10.16 Wall Thimble H. Install Vertical Termination CapI. Install Decorative Wall Components FigureFigure 10.17 Venting through the wall K. Install Horizontal Termination CapA. Fuel Conversion 11 Gas InformationB. Gas Pressure Ensure adequate ventilation C. Gas ConnectionD. High Altitude Installations Valve Pressure Taps12 Electrical Information A. Wiring RequirementsB. IntelliFire Ignition System Wiring C. Optional Accessories RequirementsE. Junction Box Installation D. Electrical Service and RepairA. Framing and Finishing Instructions 13 FinishingDrywall gypsum board Plywood Figure 13.3 Finishing Details NON-COMBUSTIBLEBOARDFinishing Around Opening with Gypsum Wallboard FIREPLACE OPENING15-7/8IN. TO 16-1/8IN Finish and Sealing JointsB. Mantel and Wall Projections Non-CombustibleFinish Materials C. Facing Material0 - 1 inch thickness-OverlapFit Method 3/4 IN Non-CombustibleFinish Materials0 Inches to 4 Inches Thick Inside Fit Method Non-CombustibleFinish Material 0-4Inches ThickInside and Overlap Fit See Section 13.C D. Decorative FrontsTable 1. Dimensions of Tonic Decorative Front Table 1. Dimensions of Tonic Decorative FrontD. Accessories 14 Appliance SetupA. Remove Fixed Glass Assembly C. Clean the ApplianceNO GLASS ROCK MEDIA BETWEEN DASHED LINES PILOT SHIELD BURNER TRACKSFigure 14.4. Maintaining Media Tray Air Spaces Removing Fixed Glass Assembly F. Fixed Glass AssemblyG. Install the Mesh H. Air Shutter SettingA. IntelliFire Ignition System 15 TroubleshootingIntelliFire Ignition System - continued Inches A. Appliance Dimension Diagram16 Reference Materials Location165 mm B. Vent Components DiagramsEffective Height Length 6-1/2in169 mm B. Vent Components Diagrams continued6-11/16in 3-15/16in12IN 305mm B. Vent Components Diagrams continued15-1/2IN 394 mm 7 IN 178 mmDESCRIPTION COAXIAL to COLINEAR VENTINGB. Vent Components Diagrams continued Optional Wire Harness2-3/4in B. Vent Components Diagrams9 in 12-1/2inStocked Service PartsC. Service Parts SLR-CCOSMOat Depot Service Parts#11 Valve Assembly SLR-CCOSMOStocked Service PartsSLR-CCOSMO at DepotNOTES D. Contact InformationNOTICE