1. Top Vent - Horizontal Termination - (continued)
Top Vent - Horizontal Termination
Venting with 3 elbows
SLR-C
V1 Minimum | H1 + H2 Maximum | V2 | V1 + V2 Minimum | ||
90° Elbow | 6 ft. | 1.8 m | * | * | |
1 ft. | 305 mm | 10 ft. | 3.0 m | * | * |
2 ft. | 610 mm | 12 ft. | 3.7 m | * | * |
3 ft. | 914 mm | 14 ft. | 4.3 m | * | * |
H1 + H2 MAX. =14 ft. (4.3 m)
V1 + V2 + H1 + H2 MAX. = 40 ft. (12.2 m)
*No specific restrictions on this value EXCEPT V1 + V2 + H cannot exceed 40 ft. (12.2 m)
Note: Use SLP Series components only.
Note: There MUST be a 25% reduction in total H when using flex vent except when using the simple up and out installation (see Figure 7.3).
H2
CAUTION: The
V2
H1
V1
Figure 7.6