Heat & Glo LifeStyle 6000GCF-IPI Vertical Penetration Framing, Installing the Ceiling Firestop

Page 19

C. Vertical Penetration Framing

WARNING

Fire Hazard

Keep loose materials or blown insulation from touching the vent pipe.

National building codes recommend using attic shield to keep loose materials/ blown insulation from contacting vent.

Hearth & Home Technologies requires the use of an attic shield.

Installing the Ceiling Firestop

Frame an opening 10 inches by 10 inches whenever the vent system penetrates a ceiling/floor (see Figure 6.4).

Frame the area with the same sized lumber as used in ceiling/floor joist.

When installing a top vent vertical termination appliance the hole should be directly above the appliance, unless the flue is offset.

Do not pack insulation around the vent. Insulation must be kept away from the pipe.

Installing Attic Shield

Note: An additional ceiling firestop is not required if attic shield is used.

• Frame opening for attic shield.

ATTIC ABOVE

10 IN. (254 MM)

10 IN.

(254 MM)

HOLE SHOULD MEASURE

10 IN. X 10 IN.

(254 MM X 254 MM)

INSIDE TO INSIDE

Figure 6.4

• Attic shield may be installed above or

 

 

 

below ceiling (see Figure 6.5).

 

 

• Secure with three fasteners on each

BEND TABS IN

 

 

side.

AROUND PIPE

 

 

 

 

Fold tabs at top of attic shield in toward

3 FASTENERS

 

 

vent pipe. Tabs must keep vent pipe

PER SIDE

 

 

 

 

 

centered within shield.

 

 

Field construct additional shield height if

 

 

 

insulation is deeper than height of attic

ATTIC SHIELD INSTALLED

ATTIC SHIELD INSTALLED

 

shield.

BELOW CEILING

ABOVE CEILING

 

 

Figure 6.5 Installing the Attic Shield

 

 

Heat & Glo • 6000GCF-IPI, 6000GCF-IPILP2110-900 Rev. F • 6/08

19

Image 19
Contents Hot glass will cause burns Models 6000GCF-IPI6000GCF-IPILPHomeowner Reference Information CongratulationsTable of Contents Listing and Code Approvals Requirements for the Commonwealth of Massachusetts Installation of Carbon Monoxide DetectorsTools and Supplies Needed Getting StartedSelecting Appliance Location Framing and ClearancesClearances Constructing the Appliance ChaseIn. MIN Mantel ProjectionsFt. MAX Vent Termination Minimum Clearances Termination LocationsSee .4 for specific clearances Alcove Applications Measuring Standards Vent Information and DiagramsVent Table Key Use of ElbowsMinimum Maximum Vent DiagramsTop Vent Horizontal Termination One Elbow Two ElbowsTop Vent Horizontal Termination Three Elbows H1 Maximum V1 + Minimum H1+ H2 V1+ V2 Minimum H1+ H2 Maximum Top Vent Vertical Termination Three ElbowsPipe Clearances to Combustibles Vent Clearances and FramingCombustible Wall Penetration Wall Penetration FramingNon-Combustible Wall Penetration Installing Attic Shield Installing the Ceiling FirestopVertical Penetration Framing Appliance Preparation Temporary Access PanelAttaching Sheetrock Ledges Securing and Leveling the Appliance Installing the Flue RestrictorVertical Top Vent Installing the Fiberglass GasketAssembling Pipe Sections Installing Vent PipeAssembly of Vent Sections Attaching Vent to the Firebox AssemblyAssembling DVP-12A Slip Sections Assembling Minimum Installations MI SectionsSecuring the Vent Sections Vertical Sections Disassembly of Vent SectionsHorizontal Sections Installing the Horizontal Termination Cap Installing Heat Shield and Horizontal Termination CapHeat Shield Requirements for Horizontal Termination Roof Pitch Min. Ft Installing Roof Flashing and Vertical Termination Cap17 Assembling the Storm Collar Around the Pipe Assembling and Installing Storm CollarPressure Natural Gas Propane Gas InformationFuel Conversions Gas Connection Gas PressuresHigh Altitude Installations Electrical Information Recommendation for WireWall Switch Optional Accessories RequirementsIntellifire Pilot Ignition IPI Wiring Diagram Wall Switch Installation for Fan Optional Junction Box InstallationFacing Material FinishingRemove Shipping Materials Appliance SetupClean the Appliance AccessoriesEmber Placement Install the RefractoryPlacing the Ember Material Log #1 SRV2103-107 Positioning the Logs12 Front View Grilles and Trim Glass AssemblyAir Shutter Setting Screen MeshBefore Lighting Appliance Operating InstructionsFinal inspection by Turn off all electric power to the applianceOn position. The ON/OFF switch may Lighting Appliance IPI IgnitionInitial Break-in Procedure Frequently Asked QuestionsAfter Appliance is Lit Intellifire Ignition System TroubleshootingSympton Possible Cause Corrective Action Symptom Possible Cause Corrective Action Maintaining and Servicing Appliance Maintenance TasksDoors, Surrounds Inspect Maintenance TasksReference Materials Appliance Dimension DiagramLocation Inches Millimeters DVP vent components Vent Components DiagramsHorizontal Termination Cap Kit Horizontal Termination CapWall Shield Firestop Heat ShieldNot for use on these models Extended Heat ShieldDVP-HRC-SS DVP-HRC-ZC-SS Horizontal Termination CAP Log Set Assembly Part number list on following Service PartsStocked Service Parts ListAt Depot 6000GCF-IPI IPI Valve AssemblyLimited Lifetime Warranty Heat & GLO GAS Appliance Products Limited Lifetime WarrantyDo not Discard this Manual Contact Information