5.Base Rail
a.Unit shall have base rails on a minimum of 2 sides.
b.Holes shall be provided in the base rails for rigging shackles to facilitate maneuvering and overhead rigging.
c.Holes shall be provided in the base rail for moving the rooftop by fork truck.
d.Base rail shall be a minimum of 16 gauge thickness.
6.Condensate pan and connections:
a.Shall be a sloped condensate drain pan made of a
b.Shall comply with ASHRAE Standard 62.
c.Shall use a 3/4”
7.Top panel:
a.Shall be a single piece top panel on 04 thru 12 sizes, two piece on 14 size.
8.Gas Connections:
a.All gas piping connecting to unit gas valve shall enter the unit cabinet at a single location on side of unit (ho- rizontal plane).
b.
(1.) Standard unit shall have a
(2.) Optional, factory approved,
(3.) No basepan penetration, other than those authorized by the manufacturer, is permitted.
9.Electrical Connections
a.All unit power wiring shall enter unit cabinet at a single, factory prepared, knockout location.
b.
(1.) Standard unit shall have a
(2.) Optional, factory approved,
(3.) No basepan penetration, other than those authorized by the manufacturer, is permitted.
10.Component access panels (standard)
a.Cabinet panels shall be easily removable for servicing.
b.Unit shall have one factory installed,
c.Panels covering control box, indoor fan, indoor fan motor, gas components (where applicable), and com- pressors shall have molded composite handles.
d.Handles shall be UV modified, composite. They shall be permanently attached, and recessed into the panel.
e.Screws on the vertical portion of all removable access panel shall engage into heat resistant, molded compos- ite collars.
f.Collars shall be removable and easily replaceable using manufacturer recommended parts.
23 81 19.13.I. Gas Heat
1.General
a.Heat exchanger shall be an induced draft design. Positive pressure heat exchanger designs shall not be al- lowed.
b.Shall incorporate a
c.Gas supply pressure at the inlet to the rooftop unit gas valve must match that required by the manufacturer.
2.The heat exchanger shall be controlled by an integrated gas controller (IGC) microprocessor.
a.IGC board shall notify users of fault using an LED
b.The LED shall be visible without removing the control box access panel.
c.IGC board shall contain algorithms that modify evaporator fan operation to prevent future cycling on high temperature limit switch.
d.Unit shall be equipped with
3.Standard Heat Exchanger construction
a.Heat exchanger shall be of the
b.Burners shall be of the
580J