Hearth and Home Technologies SL-550TRSI-AUE manual Flue Termination

Page 21

If the area above the ceiling is NOT an attic, position and secure the ceiling firestop on the ceiling side of the previously cut and framed hole.

 

JOIST

CEILING

 

NAILS (4 REQUIRED)

CEILING FIRESTOP

 

Figure 26. Ceiling Firestop (Ceiling Side)

If the area above the ceiling IS an attic, position and secure the firestop on top of the previously framed hole.

NAILS (4 REQUIRED)

RAFTER

CEILING

CEILING FIRESTOP

Figure 27. Attic Firestop

C. Flue Termination

For Horizontal Terminations using the DVP-TRAP To attach and secure the termination to the last section of horizontal flue:

The rear flue heat shield MUST be placed one inch above the top of the flue between the wall shield and the base of the termination cap.

One section of the heat shield is attached to the wall shield. The other is attached to the termination cap in the same manner (see Figure 28).

The heat shield sections will overlap to match the wall thickness (depth).

If the wall thickness does not allow the required 1-1/ 2 inch heat shield overlap, an extended heat shield must be used. The extended heat shield will need to be cut to the thickness of the wall and be at- tached to the wall shield.

The small leg in the shield rests on top of the flue to properly space it from the pipe section (see Figure 28).

Interior

Rear Vent

Wall Shield

Heat Shield

 

38mm min.

 

overlap

Outer Flue

 

Inner Flue

38mm min.

 

 

Overlap

INTERIOR

EXTERIOR

 

Figure 28. Venting through the Wall

The termination kit should pass through the wall firestops from the exterior of the building.

Adjust the termination cap to its final exterior posi- tion on the building and interlock the flue sections.

!WARNING: THE TERMINATION CAP MUST BE POSITIONED SO THAT THE ARROW IS POINTING UP.

Use a high-temperature sealant gasket to seal be- tween the pipe and exterior firestop.

Heat & Glo • SL-550TRSI-AUE2079-902 Rev. B • 7/06

21

Image 21
Contents Kensington Boulevard, Lakeville, MN 55044 USA Model SL-550TRSI-AUEHeat & Glo Quality Systems registered by SGS ICS Table of Contents Diagram of SL-550TRSI-AUE Installation Instructions Top FlueRear Flue Introduction Framing DimensionsSpace heaters Flue System Approvals Model Flue Termination ApprovalsIdentifying Flue Components DVP90ST Heat & Glo SL-550TRSI-AUE 2079-902 Rev. B 7/06 Maximum 10.97M Vertical FlueingUSE SL D-SERIES USE DVP-SERIES Components onlyUSE DVP-SERIES Components USE SL D-SERIES Components Only Flueing with ONE 1 90 ElbowFlueing with TWO 2 90 Elbows + H FT. MFT. V M FT. HM Flueing with TWO 2 90 Elbows + H1 FT. M Flueing with Three 3 90 ElbowsFlueing with Three 3 90 Elbows Installing Flue Components Assembling Flue Components Nent and the Outer Heater WrapContinue Adding Flue Components Install Support BracketsHole and New Framing Members Installing Support BracketsFlue Termination Gas Supply Line Connecting the GAS SupplyShock Risk Ignition System WiringBlower FAN Ceiling FinishingInstaller Testing Installing the TrimPilot Assembly 3 4 5 6 7 Heat & Glo SL-550TRSI-AUE 2079-902 Rev. B 7/06 Heat & Glo SL-550TRSI-AUE 2079-902 Rev. B 7/06 Operating Instructions Trol Wiring System of this UnitOperating This Appliance MAY Exhibit a Slight Carbon DepositionDo not Connect 220/240 VAC to the Control Valve Safety & Lighting InformationServicing and Maintenance Glass Door When IT is HOTFAN Operation Parts Replacement Removal of Components for ServiceAdjustments and Replacement Parts Removal of Covers for ServicingDoors Inspect Maintenance Tasks Maintenance TasksElectronic Ignition System TroubleshootingPan beneath the burne SL-550TRSI-AUE Log set assemblySL-550TRSI-AUE Service Parts List Heat & Glo SL-550TRSI-AUE 2079-902 Rev. B 7/06 Melbourne