Current Sensing Relay

Current Sensing Relay

The granulator can be equipped with an optional current sensing relay to control the feed equipment.

The current sensing relay detects the mill motor current consumption and can temporarily stop accessories such as conveyors, roller feeders etc to avoid putting further material into the hopper, when the mill is running under heavy loading.

The relay stops and re-starts accessory equipment automatically,

without re-setting.

C

T1

 

 

Relay functions and normal settings:

 

 

T1

Start delay, prevents the relay from breaking

 

 

 

 

on connection (0.1 - 10 sec).

 

 

 

 

The default start delay is 0.1 seconds.

 

 

T2

Reaction time, prevents the relay from breaking

 

 

 

 

during temporary high loading (0.1 - 3 sec).

 

 

 

 

Default reaction time is 3.0 seconds.

 

 

A– Hysteresis, adjustable between 5 - 50% of the set limit.

Default hysteresis is 20 %.

B

Limit value, adjustable between 0 - 100 %.

A

T2 B

 

 

Default setting depends on the current transformer size.

 

 

 

Check the current transformer size and then check the

 

 

 

default setting for this granulator.

 

 

C

Relay function, N = normal; I = inverted;

 

 

9 Wiring Diagram

W i r i n g D i a g r a m l 9 - 3

Image 67
Contents Models CHS-810, CHS-814, CHS-819, and CHS-824 CHS Tangential Feed GranulatorsDate Manual Number UGG011/0504 Serial Numbers Model Numbers Installation Table of ContentsTechnical Specification 4. Safety Instructionsi i l Ta b l e o f C o n t e n t s ServiceSpare Parts List Wiring Diagram12. Transport and Storage 11. Accessories, OverviewA. Customer Service 10. Layouti v l Ta b l e o f C o n t e n t s AT T E N T I O N I n t r o d u c t i o nP u r p o s e o f t h e U s e r G u i d e . . . . . . . . . . . . . 1 H o w t h e G u i d e i s O r g a n i z e d . . . . . . . . . . . . 1How the Guide is Organized Purpose of the User GuideYour Responsibility as a User WARNING Voltage hazard AT T E N T I O N Read This so no One Gets Hurt1 I n t r o d u c t i o n This manual applies to the CHS series of Conair granulators Technical Specifications Technical SpecificationsTechnical Specifications l 2 SPECIFICATION NOTES Hardened cutter housing2 - 2 l Technical Specifications Performance characteristicsFunction Description Function DescriptionG e n e r a l S a f e t y S y s t e mGeneral Function Descriptionmodels with a conveyor, the hopper is equipped with a conveyor belt. The conveyor can be equipped with a metal detector Safety Switch Safety SystemEmergency Stop Before Starting Star Knob3 - 6 l Function Description 4 S a f e t y I n s t r u c t i o n s Safety InstructionsS a f e t y I n s t r u c t i o n s l 4 If the rotor must be turned manually - do this with great care Safety InstructionsElectrical installation must only be done by a competent electrician During maintenance, pull out the plug on the distribution boxDANGER! Cutting or pinch risk DANGER! High voltageDANGER! Be careful 4 - 4 l S a f e t y I n s t r u c t i o n s I n s t a l l a t i o n l 5 I n s t a l l a t i o nPre-Start Checks I n s t a l l a t i o nTwo Hours After First Start If any direction of rotation should be incorrect Electrical ConnectionThe granulator should be connected by a competent electrician Check the direction of rotation of the granulator motorscreen box, switch both the main switch and Opening of Hopper, Screen Box and Granule BinOpening the hopper Opening the screen boxThere is a pinch risk during closing, be careful Close the screen box and install the granule binClosing the Screen Box, Granule Bin and Hopper Close the hopper5 - 6 l M a i n t e n a n c e S t a r t i n g a n d S t o p i n g Operation and Daily MaintenanceMaintenance Operation and Daily Maintenance l 6Starting and Stopping Operation and Daily Maintenance6 - 2 l Operation and Daily Maintenance Monthly Inspection InspectionDaily Inspection Weekly InspectionSwitch “Off” both the main switch and the switch on the granulator Cleaning6 - 4 l Operation and Daily Maintenance Re-install after cleaning 6 - 6 l Operation and Daily Maintenance Fault-FindingThe granulator does not start Operation and Daily Maintenance l 6 6 - 8 l Operation and daily maintenance S e r v i c e Changing the knives ServiceChanging the knives Removing the knivesFirst install the rear, fixed knife Installing the KnivesInstall the rotating knives 6 Install screws A with washers B, and tighten so that they hold Then install the front, fixed knife Sharpening Knives - Granulators with Open Cutter Sharpening KnivesGrind the cutting angle of the knives to Transmission V-Belts, Inspection, and AdjustmentThe granulator is driven by 3 V-belts Checking the V-belts V-belt Adjustment Transmission continuedCutter Housing Lubrication7 - 1 0 l Service Cutter Pulley InstallingCutter Pulley/Motor Pulley Removal7 - 1 2 l Service S a f e t y Spare Parts ListOrdering Spare Parts Spare Parts ListArt. no Cutting ChamberDescription 8 - 4 l S p a r e P a r t s L i s t Staggered RotorArt. no DescriptionParts Open RotorList SpareKnives Knives, Open Cutter8 - 6 l S p a r e P a r t s L i s t Spare Parts Screen Box Screen8 - 8 l S p a r e P a r t s L i s t Granule Bin Manual Optional Art. no Vaccum Suction /Blower F-7/F-158 - 1 0 l S p a r e P a r t s L i s t Pos QtyHopper 8 - 12 l S p a r e P a r t s L i s t Hopper - Noise encapsulated machine with with ConveyorS p a r e P a r t s L i s t l 8 - 1 Hopper Device8 - 14 l S p a r e P a r t s L i s t Sound Cabin8.17 Enclosure/Body 8 - 1 6 l S p a r e P a r t s L i s t SafetyW i r i n g D i a g r a m l 9 Wiring Diagram9 Wiring Diagram W i r i n g D i a g r a mWiring diagram Relay functions and normal settings Current Sensing RelayDefault setting for this granulator ConnectionRelay Setting Example9 - 6 l W i r i n g D i a g r a m 1 0 Layout L a y o u t1 0 - 2 l L a y o u t Layout1790mm70.47in 1490mm58.66in1650mm64.96in 27.56in.700mm1 0 - 4 l L a y o u t 1 1 Accessories A c c e s s o r i e sOrdering Spare Parts A c c e s s o r i e sSetting Up the Knives Pre - Setting of Rotating Knives, Granulator with Open CutterInstallation of Pre-Set Knives Tighten the fastening screws, tightening torque 162.26lb-ft 220 Nm Third Fixed Knife InstallationSharpening The band conveyor should be connected up by an authorised electrician SafetyBand Conveyor Electrical ConnectionIf the belt moves obliquely MaintenanceTrouble-shooting Starting11 - 8 l A c c e s s o r i e s Spare Parts for the Band ConveyorStoreage Transport and StorageU n p a c k i n g a n d C h e c k i n g Transport andPositioning in Place of Use Transport and storageLifting and Transport to Place of Use Unpacking and CheckingLong-Term Storage/Conservation Storage1 2 - 4 l T r a n s p o r t a n d S t o r a g e From outside the United States, call How to Contact Customer Ser viceWe’re Here to Help Before You CallA - 2 l A p p e n d i Equipment GuaranteePerformance Warranty Warranty Limitations