Compact Station TKS-CS - Operating Instructions
8000043213 BAL Page 33 of 39
5. Place a new transformer in the compact station's trough and
establish the connections. Finally, replace and align the roof
structure, and establish the screw connections ( transformer
operating instructions).
10.3.2.2 Replacing the MV Switchgear
1 2
3 4
Figure 21 - Partial top view TKS-CS (example)
1 Transformer compartment
2 Low-voltage box
3 Medium-voltage compartment
4 MV switchgear
1. Disconnect the equipment safely.
2. Remove all connections from the MV switchgear, and secure
the equipment.
3. Unscrew the screws of the MV switchgear and remove it from
the compact station using an industrial truck ( MV switchgear
BAL).