Manual Bypass Operation
During manual bypass operation, the critical load is supplied directly by utility power, making it possible to isolate the UPS and the Bypass Static Switch for maintenance.
Battery power is not available as an alternate power source while the system is running in manual bypass operation.
Note
A
CAUTION!
Do not open Q3 when the UPS is in manual bypass operation, as this action may result in a load drop or a failure of the UPS to support the load.
Bypass Static Switch
Delta inverter
Main inverter
Battery
Breaker Identification
Q1 | UPS input breaker | Q5 | Static bypass input breaker |
|
|
|
|
Q2 | UPS output breaker | Q7 | Battery breaker 1 |
|
|
|
|
Q3 | Manual bypass breaker | Q8 | Battery breaker 2 |
|
|
|
|
Only operate a breaker when the associated breaker lamp is on.
Note
34 | Symmetra® MW with Internal Bypass Static Switch - User Guide - |