UPS Start-Up Screen
From the UPS Start-Up screen, the power flow can be transferred from Manual Bypass to Online Operation.
Manual bypass/Off
Normal
UPS Startup
5.40 PM
Close Q1 | Display will be off until Q1 closed |
Close breaker Q5 | SSW input |
| |
Charge DC Capacitors | Initiate Charge |
Close battery breakers Q7 and Q8 | Connect battery |
Close breaker Q2 | UPS output |
Initiate transfer to static bypass | Initiate transfer |
Open breaker Q3 | Manual bypass |
Push UPS "ON" button | UPS will power up |
The UPS Start-Up screen shows a list of actions, which need to be completed in order to start up the UPS from Manual Bypass Operation. The actions are initially indicated in red to show that they have not yet been completed. A yellow bar will highlight the actions in the order in which they need to be completed. As actions are completed they will change to green.
The Start-Up procedure is described in “System Start-Up from Manual Bypass Operation” .