Operation – Operation Procedures
How to perform a restart
Restart – single system wihout external MBP.
Only trained personnel familiar with the construction and the equipment may
restart the UPS.
Warning
Set the utility/mains breaker to the ON position.
If your installation includes an XR Battery Enclosure (SUVTBXR2B6S/SUVTBXR6B6S) with a DC disconnect switch, set the DC disconnect switch to the ON position.
Wait approximately 30 seconds for the system to boot up and carry out a self test.
Note
After system
Voltage confirmation. At restart, the display will prompt you through the following screens:
Use
Confirm Voltage
Use 400V
Yes, use 400V
No, select another
Press Use
Apply load?
Yes
No
Press
When the Confirm Voltage prompt appears on the screen, go to the desired voltage using the UP/ DOWN keys and press ENTER.
When the prompt Apply load appears, go to Yes using the UP/DOWN keys and press ENTER if you want the UPS to provide a load output now. (If you do not want UPS load output at this point, go to No).
Chrg xxx%
Load xxx%
xxxVin xxxVout xxHz
The green (LOAD ON) LED is now lit. Press ESC two times and the display will show the above Overview Screen.
The UPS is now ready to support the load.
Note
19 |