Operation – Operation Procedures

How to perform a restart

Restart – single system wihout external MBP.

Only trained personnel familiar with the construction and the equipment may

restart the UPS.

Warning

Set the utility/mains breaker to the ON position.

If your installation includes an XR Battery Enclosure (SUVTBXR2B6S/SUVTBXR6B6S) with a DC disconnect switch, set the DC disconnect switch to the ON position.

Wait approximately 30 seconds for the system to boot up and carry out a self test.

Note

After system boot-up, the display will automatically ask you to confirm/select voltage and frequency as shown in the following.

Voltage confirmation. At restart, the display will prompt you through the following screens:

Use

Confirm Voltage

Use 400V

Yes, use 400V

No, select another

Press Use

Apply load?

Yes

No

Press

When the Confirm Voltage prompt appears on the screen, go to the desired voltage using the UP/ DOWN keys and press ENTER.

When the prompt Apply load appears, go to Yes using the UP/DOWN keys and press ENTER if you want the UPS to provide a load output now. (If you do not want UPS load output at this point, go to No).

Chrg xxx%

Load xxx%

xxxVin xxxVout xxHz Run-time: xxhr xxmin

The green (LOAD ON) LED is now lit. Press ESC two times and the display will show the above Overview Screen.

The UPS is now ready to support the load.

Note

990-2282A-001

Smart-UPS® VT 10-40 kVA 400V, 208V, 200V – Operation

19

Page 25
Image 25
APC VT manual How to perform a restart