Operation Procedures

How to turn into bypass

Single System – turning into internal bypass.

The load is not protected by the UPS and the power is not conditioned when the internal mechanical bypass lever is activated.

Caution

In bypass operation the batteries are still charged. If a total power off is required, the batteries must be pulled out to the red disconnect line, see the section How to perform a total power off.

Warning

This procedure is not applicable to parallel systems as the internal mechanical bypass lever is unavailable.

Note

If the UPS is running and controllable through the display, carry out steps 1 through 5. If not, go directly to step 6.

Note

Chrg 100%

Load 000%

xxxVin 000Vout x0Hz Runtime: 0hr 0m

Use

UPS into Bypass Do Self Test Simulate Power Fail Start Runtime Cal

Press

Use

Press

 

Control

Logging

 

Status

Display

 

Setup

Diags

 

 

Help

Press

Use

Press

 

Confirm:

 

 

UPS into

Bypass

 

NO, ABORT

 

 

YES, UPS

into Bypass

Check that the UPS is in bypass. The green

Remove the Front Panel from the UPS (see

(LOAD ON) and the yellow (BYPASS) LEDs

the Receiving and Unpacking sheet referred

are lit.

to under the section Companion manuals).