FC Activity – This LED blinks to show activity occurring on the Fibre Channel port of the unit. The LED may appear to be steadily lit during times of very high activity.
SCSI 1 Activity, SCSI 2 Activity – One LED for each SCSI bus displays activity on that SCSI bus.
Ready – A few seconds after power has been applied, the Ready LED should be illuminated. This indicates that the FibreBridge has passed its power on
Ethernet Port
The 10/100 BaseT Ethernet port provides SNMP and Telnet based monitoring and management through a command line interface, menu system or graphical interface (BridgeTools). Refer to the FibreBridge Software manual and the BridgeTools manual for details on the available commands for communication with the bridge.
Serial Port
The
Installation and Removal
Note that since the FibreBridge modules are hot swappable, it is not necessary to turn power off to install or remove bridge modules.
To install a FibreBridge module:
Step 1. Slide the bridge module into the rack enclosure until you feel it make contact with the backplane connector. The face of the bridge module should be flush against the rack enclosure edges.
Step 2. Secure the bridge module by tightening the two thumbscrews (hand tight).
Step 3. If not already done, apply power to the rack enclosure.
Step 4. The Fibre Channel and SCSI activity LEDs will blink for three or four seconds during the module’s power on
The correct method for removal of a bridge module is as follows:
Step 1. Disconnect all cables from the face of the bridge module.
Step 2. Loosen the two thumbscrews on the face of the bridge module.
Step 3. Carefully slide the bridge module out of the rack enclosure.