Pre-Start Inspection and Operation

WARNING

In extremely cold weather fully warm machine to prevent a possible machine run-away condition.

Machine Shut-down

To safely shut the machine down, the operator must:

1.Park the machine on a solid, level area.

2.Lower the trencher boom to the ground.

3.Idle the engine for 5 - 10 minutes to allow the machine to cool down.

4.Shut off the engine.

5.Clean off any accumulated mud and/or dirt from the machines operating surfaces, i.e. operator’s platform, both track assemblies, trencher chain assembly, etc.

Transportation

1.Move the throttle control lever to the mid-range engine speed. Raise the boom so that it will clear the ramp of the transport trailer.

NOTICE

It is recommended to back the machine onto the transport trailer and position the

machine so that the heaviest weight (center of balance) is towards the

front (hitch end) of the trailer. See Figure 3–6.

CAUTION

The Boxer is designed for maximum working balance. When traveling on an incline, always have the heaviest portion of the machine pointing uphill.

2. Follow general load carrying safety. Always carry the heaviest load pointing uphill.

3

2

1

2434

Figure 3–6 Transport Position on Trailer

3-8