C H A P T E R 2
Switch Installation
Read the topics and perform the procedures in this order:
•Warnings, page
•Installation Guidelines, page
•Verifying Switch Operation, page
•Installing the Switch, page
•Installing and Removing SFP+ and SFP Modules, page
•Inserting and Removing the SFP+ Module Patch Cable, page
•Connecting to the 10/100/1000 Ports, page
•Connecting to
•Where to Go Next, page
Warnings
These warnings are translated into several languages in the Regulatory Compliance and Safety Information for the Cisco ME 3800X and ME 3600X Switches document that ships with the switch.
These warning statements apply to all the switches:
Warning Before working on equipment that is connected to power lines, remove jewelry (including rings, necklaces, and watches). Metal objects will heat up when connected to power and ground and can cause serious burns or weld the metal object to the terminals. Statement 43
Warning Do not stack the chassis on any other equipment. If the chassis falls, it can cause severe bodily injury and equipment damage. Statement 48
Warning Ethernet cables must be shielded when used in a central office environment. Statement 171
Cisco ME 3800X and ME 3600X Switch Hardware Installation Guide
|
| ||
|
|