Installation 21
in the concrete floor, the secondary anchor locations may be used. An optional cabinet isolation kit is available consisting of four anchor bushings and a base pad. If this kit is installed, place the pad on the floor and the bushings on the anchors, and position the cabinet on top.
Figure 3 - Anchoring the cabinet
600 mm
(23.56 po.)
SECONDARY LOCATION FOR FLOOR ANCHORS
PRIMARY LOCATION FOR FLOOR ANCHORS
520 mm
+ +
526mm
(20.68 po.)
(20.42 po.)
) .
mo m p
3 0 1
93
52 (.
Procedure 2 - Installing a rectifier in a cabinet
Step | Action |
1Loosen and remove the screws securing the mounting brackets to each side of the rectifier.
2Reposition and secure the mounting brackets to the holes located nearest the front of the rectifier, on each side of the rectifier.
3Remove the blank panel from the cabinet and put the self tapping screws in a secure location, for future use.
continued
Emerson Energy Systems | Rectifier 200I/48 NT5C05C Installation and User Manual |