Maintenance 51

 

Procedure 11 - Calibrating the meter

 

 

 

 

 

 

 

Step

 

Action

 

1

Make sure the remote sense leads are disconnected by removing

 

 

the corresponding RC− fuse from the controller.

 

2

Set the VOLT/AMP switch to AMP. Set the output load of the plant

 

 

so the rectifier delivers a current of approximately 100 A. Measure

 

 

the voltage between VOUT+ and VOUT − , located on the front panel,

 

 

with a digital meter.

 

 

 

3

Convert this measured voltage to a current value ( 50 mV

 

 

corresponding to 250 A ).

 

 

 

 

current

= 250 A

 

 

voltage

50 mV

 

 

If the voltage measured is 20.2 mV :

 

 

measured current

=

250 A X ( 20.2 mV ) = 101 A

 

 

 

 

50 mV

 

 

Rotate the CUR CAL potentiometer on the display panel until this

 

 

value is displayed.

 

 

 

4

Put the VOLT / AMP switch to VOLT. Adjust the V CAL

 

 

potentiometer so that the reading displayed on the meter of the

 

 

rectifier is identical to the reading on the digital meter.

 

5

Put the rectifier to OFF and reconnect the sense leads.

 

 

end

 

6.4.Resetting the rectifier after an HVSD ( high voltage shutdown )

To reset the rectifier after an HVSD condition has occurred execute one of the steps contained in Procedure 12.

Procedure 12 - Resetting the rectifier after a high voltage shutdown

Step Action

Locally

1Toggle the ac circuit breaker on the unit itself, or the associated ac breaker in the distribution panel OFF and ON ( wait until the green ac ON LED extinguishes before toggling the breaker back to ON ).

Remotely

2Apply a ground signal at the HVSDR input of the rectifier.

end