6. ACCEPTANCE TESTS
6.9.3 INTERNAL ARC TEST
1.Change setpoint GENERAL/FUNCTION PERMIT/50BF 3P FUNCTION to NO PER.
2.Change setpoint TABLE 1/INTERNAL ARC SETTINGS/INT ARC TIMER to 2s.
3.Energize digital input CC4 52/b A
4.Apply 2A to terminals
5.Check that after INT ARC TIMER time delay, contact
6.Repeat steps 3, 4 and 5 for phases B (terminals
6.9.4 3P NO I FUNCTION
1.Change setpoint GENERAL/FUNCTION PERMIT/50BF 1P FUNCTION to NO PER.
2.Change setpoint GENERAL/FUNCTION PERMIT/50BF 3P FUNCTION to NO PER.
3.Change setpoint GENERAL/FUNCTION PERMIT/3P No INT FUNCT to PER.
4.Change setpoint TABLE 1/50BF SETTINGS/Nº OUTPUT STAGES to 1
5.Change setpoint TABLE 1/50BF SETTINGS/ 3P NO I TIMER T3 to 1s
6.Change setpoint TABLE 1/50BF SETTINGS/LOW LOAD 2P to PER.
7.Energize digital input CC7 3P BF INITIATE. If the relay has not an expansion board, energize CC1 PHASE A BF INITIATE and CC2 PHASE B BF INITIATE.
8.Check that after 3P NO I TIMER T3 (2s), the following contacts are closed:
9.If the relay is provided with an expansion board, check that also the following contacts are closed:
6.9.5 NEUTRAL OVERCURRENT UNIT TEST
1.Change setpoint GENERAL/FUNCTION PERMIT/50BF 1P FUNCTION to NO PER.
2.Change setpoint GENERAL/FUNCTION PERMIT/50BF 3P FUNCTION to NO PER.
3.Change setpoint GENERAL/FUNCTION PERMIT/3P No INT FUNCT to PER.
4.Change setpoint TABLE 1/50BF SETTINGS/LOW LOAD 2P to PER.
5.Energize digital inputs CC4, CC5 and CC6 (52b inputs).
6.Energize digital inputs CC7 3P BF INITIATE. If the relay has not an expansion board, energize digital inputs CC1 PHASE A BF INITIATE and CC2 PHASE B BF INITIATE.
7.Apply 2A to terminals
DBF Breaker Failure Protection | 35 |