4.5.6.3 Notes concerning use / maintenance of a parallel system
ECO-mode:
If
No-load shutdown:
If
Manual bypass:
If you want to switch one of the UPSs to bypass operation using the manual bypass switch (switch is turned into position 2) then all UPSs in the parallel system have to be switched to bypass operation in order to prevent damage.
Maintenance:
To isolate a unit from the redundant system:
1.Switch off the UPS which has to be isolated,
2.Remove the installation fuse from the input of that UPS
3.Separate the output of the UPS from the output junction
To
4.Reinstall the installation input fuse,
5.Connect the output of the UPS to the output junction,
6.Switch on the UPS.