4.5.3.3Output voltage 220/230/240Vac

1.The factory setting of the output tap (208Vac) has to be changed to 240Vac. Follow the procedure as described in section 4.5.3.2 steps 1.1 and 1.2.

2.Connect the load wires between the terminals 1 (L1) and 4 (N). Connect the ground wire to terminal 5. Ground connection is essential! Do not remove the link between terminals 2 and 3. See figure 14.

Figure 14. LP 5/6/8/10-11U:

220/230/240 Vac output connection

3.Return to either 4.5.1.1 step 5 or 4.5.1.2 step 5

4.5.3.4Output voltage 120Vac single phase

1.The factory setting of the output tap (208Vac) has to be changed to 240Vac. Follow the procedure as described in section 4.5.3.2 steps 1.1 and 1.2.

2.Remove the link between terminals 2 and 3.

3.Place this link between terminal 1 and 2.

4.Place the extra link (delivered with the unit) between terminals 3 and 4.

5.Connect the load wires between connectors 1 (or 2) and 3 (or 4).

For LP 8/10kVA: If the wire size does not allow to place two wires (i.e. load wire and link) in one terminal, proceed with step 8.

6.Connect the ground wire to terminal 5. Ground connection is essential!

7.Return to either 4.5.1.1 step 5 or 4.5.1.2 step 5.

Figure 15. LP 5/6/-11U:

120 Vac single phase output connection

LX: OPM_LPU_11U_5K0_10K_1US_V030